*Proposed location of development features (buildings, roads, utilities, etc.).
 
*Proposed location of development features (buildings, roads, utilities, etc.).
 
===Sampling===
 
===Sampling===
 +
The number of test pits or soil borings varies depending on site conditions and the proposed development plan. General guidelines are as follows:
 +
 +
*For infiltration BMPs with footprint surface areas from 50 - 900 m<sup>2</sup>, a minimum of two test pits or one test pit and two soil borings are required at, or within 10 m of the proposed location to determine the suitability and distribution of soil types present;
 +
*For infiltration BMPs with footprint surface areas > 900 m<sup>2</sup>, a minimum of one test should be conducted for each 450 m<sup>2</sup> of footprint area. Tests should be conducted equidistant from each other to provide adequate characterization of the area;
 +
*For linear infiltration BMPs (e.g. [[bioswales]], [[enhanced grass swales]], [[infiltration trenches]], [[exfiltration trenches]]) a minimum of one test should be conducted within each soil mapping unit present along the proposed BMP location. Soil borings should be conducted every 50 m and a test pit should be conducted every 450 m; and
 +
*For sites with multiple infiltration BMPs, each with footprint surface area < 50 m<sup>2</sup>, a minimum of one test pit is required and one soil boring per infiltration BMP location is recommended.
    
*The recommendations above are guidelines. Additional tests should be conducted if local conditions indicate significant variability in soil types, geology, water table levels, depth and type of bedrock, topography, etc.
 