==Overflows==
 
==Overflows==
 +
[[Overflow|Overflows]] are features of inline facilities and convey larger storm events out of the LID feature.
   −
{{:Overflow: Installation}}
+
'''Construction Steps:'''
 +
#Connect the overflow drain to the underdrain.
 +
#Fit a metal, domed grate to the overflow.
 +
#Install overflow pit to grade at the location specified in the contract documents.
 +
 
 +
'''Key Inspection Points:'''
 +
*Overflow drain matches design specifications.
 +
*Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents.
 +
*Sufficient freeboard is provided between the overflow and inlet such that the inlet is not inundated by design storm flows.
 +
*Overflow grate matches design specifications.
 +
*Overflow grates located in high-traffic areas are screwed on or equipped with locks.
 +
 
 +
'''Mistakes to Avoid:'''
 +
*Backflows: Ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys.
 +
*Incorrect sequencing: Install overflow drain prior to backfilling with granular material and engineered soil.
 +
*Incorrect grate material: Avoid using plastic overflow grates due to breakages and UV degradation.
 +
 
 +
<gallery mode="packed" widths=300px heights=300px>
 +
overflow-pipe-install.jpg | Overflow pipe installed to an underdrain T-connection. (Photo Source: CVC, 2010)
 +
overflow-plastic-cap.jpg | Overflow installed with a plastic cap. Note that the use of plastic grates is discouraged. (Photo Source: CVC, 2012)
 +
 
 +