| ==Monitoring wells== | | ==Monitoring wells== |
| + | [[File:monitoring-well-subgrade.jpg|400px|thumb|right|Monitoring well stack installed next to underdrain within the LID practice. (Photo Source: CVC, 2010)]] |
| + | [[Monitoring wells]] allow for measurement of water levels in the sub-surface components of LID practices. They are important for sampling procedures and ensuring that the LID feature are performing as intended. |
| | | |
− | {{:Monitoring wells: Installation}}
| + | '''Construction Steps:''' |
| + | #Install a cap stand at the required elevation to anchor the monitoring well. |
| + | #Wrap the perforated pipe with a geotextile sock (to prevent migration of soil into the well). |
| + | #Anchor the perforated pipe to the bottom of the LID feature. |
| + | #Install a lockable cap to the top of the standpipe to protect against vandalism. |
| + | #Install monitoring equipment (e.g., a level logger) if required. |
| + | |
| + | '''Key Inspection Points:''' |
| + | *Pipe is perforated, rigid, and matches design specifications. |
| + | *Well is installed according to contract documents. |
| + | *Geotextile sock is wrapped around the perforated portion of the well. |
| + | |
| + | '''Mistakes to Avoid:''' |
| + | *Incorrect sequencing: Ensure that standpipe is installed prior to backfilling with granular material. |
| | | |
| ==Storage reservoir== | | ==Storage reservoir== |