Line 9: |
Line 9: |
| | | |
| ===Overflow elevation=== | | ===Overflow elevation=== |
− | The invert of the overflow should be placed at the maximum water surface elevation of the practice. i.e. the maximum ponding depth. A good starting point is around 300 mm over the surface of the practice. However, consideration should be given to public safety and time for the ponded water to drain. See [[Bioretention: Sizing#Additional step for system without underdrain|Bioretention]] and [[Stormwater planters]] | + | The invert of the overflow should be placed at the maximum water surface elevation of the practice. i.e. the maximum ponding depth. |
| + | A good starting point is around 300 mm over the surface of the practice. However, consideration should be given to public safety and drainage time|time for the ponded water to drain. |
| + | See [[Bioretention: Sizing#Additional step for system without underdrain|Bioretention]] and [[Stormwater planters]] |
| + | |
| + | Where temporary ponded water is being planned for, include a [[freeboard]] to reduce the chance of localised flooding. |
| | | |
| ===Options=== | | ===Options=== |