# Add water to around 3/4 full,
# Add water to around 3/4 full,
# Secure cap and shake,
# Secure cap and shake,
−
# Leave for at least 30 minutes until the water is clear - longer is better, so overnight when possible.
+
# Leave for at least 30 minutes until the water is clear - longer is better, so overnight when possible,
−
# Examine the layer of sediment - if > 3 mm has been washed from 5 cm of product, reject the material.
+
# Examine the layer of sediment - if > 3 mm has been washed from 5 cm of product, reject the material,
+
Note that the sediment may collect on top of, or at the bottom of the construction material.
+
+
==External references==
+
*Heger, S. (2014). Critical Aspects During System Installation and Inspection General equipment considerations. In PMSA conference. Retrieved from http://www.psma.net/pdf/14/conference-presentations/Keys to Installation (Heger).pdf