The required volume for a small forebay, serving up to 2 Ha (''V<sub>f</sub>'', m³), may be calculated as:
+
1. The required volume for a small forebay, serving up to 2 Ha (''V<sub>f</sub>'', m³), may be calculated as:
:<math>V_{f}=A_{c}\times R\times L_{o} \times F_{c}</math>
:<math>V_{f}=A_{c}\times R\times L_{o} \times F_{c}</math>
Line 14:
Line 14:
}}
}}
−
The area of the forebay (''A<subf</sub>'') designed for 80 % capture efficiency (i.e. R = 0.8) may be calculated as:
+
2. The area of the forebay (''A<subf</sub>'') designed for 80 % capture efficiency (i.e. R = 0.8) may be calculated as:
:<math>A_{f}=\frac{12\times Q}{V_{f}}</math>
:<math>A_{f}=\frac{12\times Q}{V_{f}}</math>
Line 23:
Line 23:
}}
}}
−
Check that the forebay depth (''d<sub>f</sub>'', m) ≤ 0.3 m:
+
3. Check that the forebay depth (''d<sub>f</sub>'', m) ≤ 0.3 m:
: <math>d_{f}=\frac{V_{f}}{A_{f}}</math>