A detention time of 24 hours should be targeted in all instances. Where this necessaitates a very low outflow, a [[Flow control#Vortex valve|vortex valve]] or similar is recommended over an orifice or pipe restiction. The detention time is approximated by the drawdown time.
A detention time of 24 hours should be targeted in all instances. Where this necessaitates a very low outflow, a [[Flow control#Vortex valve|vortex valve]] or similar is recommended over an orifice or pipe restiction. The detention time is approximated by the drawdown time.
−
The drawdown time in the pond can be estimated using Equation 4.10. Equation 4.10 is the classic falling head orifice equation which assumes a constant pond surface area. This assumption is generally not valid, and a more accurate estimation can be made if Equation 4.10 is solved as a differential equation. This is easily done if the relationship between pond surface area and pond depth is approximated using a linear regression.
The drawdown time in the pond can be estimated using Equation 4.10. Equation 4.10 is the classic falling head orifice equation which assumes a constant pond surface area. This assumption is generally not valid, and a more accurate estimation can be made if Equation 4.10 is solved as a differential equation. This is easily done if the relationship between pond surface area and pond depth is approximated using a linear regression.
−
Equation 4.10: Drawdown Time
+
<math>A_O=\frac{2A_{P}}{t\ C(2g^{0.5})}\left ( h_{1}^{0.5}-h_{2}^{0.5} \right )</math>
t = start fraction 2 A subscript p over C A subscript o left-parenthesis 2 g right-parenthesis superscript 0 point 5 end fraction left-parenthesis h subscript 1 superscript 0 point 5 minus h subscript 2 superscript 0 point 5 right-parenthesis
t = start fraction 2 A subscript p over C A subscript o left-parenthesis 2 g right-parenthesis superscript 0 point 5 end fraction left-parenthesis h subscript 1 superscript 0 point 5 minus h subscript 2 superscript 0 point 5 right-parenthesis
Line 67:
Line 66:
<ref>Ontario Ministry of Environment. (2003). Stormwater Management Planning and Design Manual. Retrieved January 15, 2017, from https://www.ontario.ca/document/stormwater-management-planning-and-design-manual/stormwater-management-plan-and-swmp-design</ref>
<ref>Ontario Ministry of Environment. (2003). Stormwater Management Planning and Design Manual. Retrieved January 15, 2017, from https://www.ontario.ca/document/stormwater-management-planning-and-design-manual/stormwater-management-plan-and-swmp-design</ref>
−
===Excess flow control===
===Excess flow control===