The following, comprehensive list is presented as a basis for discussion between regulatory authorities and design practitioners <ref>Ontario Provincial Standard Specification. (2014). Construction Specification and for Seed and Cover OPSS.PROV 804. Retrieved from http://www.raqsb.mto.gov.on.ca/techpubs/ops.nsf/0/3a785d2f480f9349852580820062910a/$FILE/OPSS.PROV 804 Nov2014.pdf</ref>.
+
The following, comprehensive list is presented as a basis for discussion between regulatory authorities and design practitioners.
+
{{TOClimit|2}}
==Site Description==
==Site Description==
* Location (key plan, municipal address, nearest roads, watershed and subwatershed);
* Location (key plan, municipal address, nearest roads, watershed and subwatershed);
Line 10:
Line 11:
==Background Information==
==Background Information==
* Pre-submission meeting verification;
* Pre-submission meeting verification;
−
* Reports from pre-consultation with MOECC and other agencies (especially related LID credits);
+
* Reports from pre-consultation with MOECP and other agencies (especially related LID credits);
* Watershed plans;
* Watershed plans;
* Sub-Watershed plans;
* Sub-Watershed plans;
Line 32:
Line 33:
**LID facility location and associated tributary areas;
**LID facility location and associated tributary areas;
* Model schematics;
* Model schematics;
−
* Storm drainage, grading and general servicing plans;
+
* Storm drainage, [[grading]] and general servicing plans;
* LID practice design [[drawings]] and details;
* LID practice design [[drawings]] and details;
* [https://sustainabletechnologies.ca/home/erosion-and-sediment-control/ Erosion and sediment control plans];
* [https://sustainabletechnologies.ca/home/erosion-and-sediment-control/ Erosion and sediment control plans];
+
+
{| class="wikitable sortable"
+
! Parameter
+
! Plan
+
! Detail
+
! Profile
+
! Description
+
|-
+
| Location
+
| x
+
|
+
|
+
| Area extent shown on plan view (bump-outs, municipal reserves, private lots, parks)
+
|-
+
| Surface area
+
| x
+
|
+
|
+
| Outlined on plan view drawings and stated in report
+
|-
+
| Inlet
+
| x
+
| x
+
|
+
| shown on plan view and typical details provided ([[curb cuts]], [[level spreader|flow spreader]], ribbon curb)
+
|-
+
| Materials
+
|
+
| x
+
|
+
| Materials specs (soil, drainage layer), depth, hydraulic conductivity, porosity
+
|-
+
| Vegetation
+
| x
+
| x
+
|
+
| Planting plan and [[vegetation]] details (species, mature density, succession plan)
+
|-
+
| Outlet
+
| x
+
| x
+
| x
+
| [[Underdrain]] spec and slope, spill elevation, catch basin type and grate, [[weir]] type and location, [[inlet]] control device details
+
|-
+
| Catchment
+
| x
+
|
+
|
+
| Delineated catchment area directed to [[bioretention]] facility
+
|-
+
| Subsurface materials
+
|
+
| x
+
|
+
| Layer order (filter, [[reservoir aggregate|reservoir]], [[choker course]], [[geotextiles]] (if using)) and specifications (gradation, hydraulic conductivity, void space)
+
|-
+
| Depth
+
|
+
| x
+
| x
+
| Depth of each layer, reservoir retention depth (if applicable), surface ponding depth (if applicable)
+
|-
+
| Slope
+
|
+
| x
+
| x
+
| Sub-base slope and surface slope
+
|-
+
| Flow Arrows
+
|
+
| x
+
|
+
| From contributing area and overflow route
+
|-
+
| Water depth
+
|
+
| x
+
|
+
| Ponding depth and water surface elevation during design storm and maximum prior to [[overflow]]
+
|-
+
| Inundation
+
|
+
| x
+
|
+
| Extent of of inundation during design storms
+
|-
+
| Erosion control
+
| x
+
| x
+
|
+
| Located at inlet, outlet if overland spill
+
|}
==Design Information==
==Design Information==
Line 42:
Line 135:
*Flow and storage summary tables provided which reference the associated drainage area, catchment ID, outlet(s) and differentiate between controlled and uncontrolled areas.
*Flow and storage summary tables provided which reference the associated drainage area, catchment ID, outlet(s) and differentiate between controlled and uncontrolled areas.
*Identify and show seasonal high groundwater levels in report and on drawings;
*Identify and show seasonal high groundwater levels in report and on drawings;
−
*Per [[https://www.ontario.ca/document/stormwater-management-planning-and-design-manual-0 MOECC SWM manual, 2003]] (i.e. Drainage area, required volume, slopes, forebay, etc.);
+
*Per [https://www.ontario.ca/document/stormwater-management-planning-and-design-manual-0 MOECC SWM manual, 2003] (i.e. Drainage area, required volume, slopes, forebay, etc.);
*The SWM report and drawings are to include a table summarizing required storage, provided storage and associated elevation and flow for the permanent pool, 25mm (extended detention), and 2 through 100 year return period storm events where applicable for each facility;
*The SWM report and drawings are to include a table summarizing required storage, provided storage and associated elevation and flow for the permanent pool, 25mm (extended detention), and 2 through 100 year return period storm events where applicable for each facility;
*An operations and maintenance manual (includings a maintenance schedule) should be included in the SWM Report for all LID facilities in accordance with municipal requirements;
*An operations and maintenance manual (includings a maintenance schedule) should be included in the SWM Report for all LID facilities in accordance with municipal requirements;
Line 61:
Line 154:
*External drainage conveyance (100 year and Regional);
*External drainage conveyance (100 year and Regional);
===Quality control===
===Quality control===
−
*Level of Protection;
+
*Level of protection;
−
*Drainage Area to Facility in hectares;
+
*Drainage area to facility in hectares;
−
*Percentage Impervious – total and directly connected areas;
+
*Percentage impervious – total and directly connected areas;
−
*SWM Facility Monitoring and Maintenance Requirements;
+
*SWM facility monitoring and maintenance requirements;
==Hazard land management==
==Hazard land management==