Excavation to the sub-grade will differ depending on whether the design is for a [[Bioretention: Variations|full infiltration, partial infiltration, or no infiltration LID system]]. If it’s a full infiltration or partial infiltration practice, the sub-grade should be as level as possible to promote even infiltration across the facility’s footprint. For no infiltration designs, excavate sub-grade slopes to the design grade in the direction of the underdrain, typically 1 to 2%. | Excavation to the sub-grade will differ depending on whether the design is for a [[Bioretention: Variations|full infiltration, partial infiltration, or no infiltration LID system]]. If it’s a full infiltration or partial infiltration practice, the sub-grade should be as level as possible to promote even infiltration across the facility’s footprint. For no infiltration designs, excavate sub-grade slopes to the design grade in the direction of the underdrain, typically 1 to 2%. |