Test pit excavations or soil borings should extend to a depth of between 2.5 - 5 m below ground surface or until bedrock or fully saturated conditions are encountered. It is important that the tests provide information related to conditions at least 1.5 m below the proposed bottom elevation of the infiltration BMP. Test pit trenches should be benched at 1 m depth intervals for access and infiltration testing. | Test pit excavations or soil borings should extend to a depth of between 2.5 - 5 m below ground surface or until bedrock or fully saturated conditions are encountered. It is important that the tests provide information related to conditions at least 1.5 m below the proposed bottom elevation of the infiltration BMP. Test pit trenches should be benched at 1 m depth intervals for access and infiltration testing. |