Changes

Jump to navigation Jump to search
Line 58: Line 58:     
==Design==
 
==Design==
 +
[[File:PermeablePaving CrossSection.png|thumb|550px|Permeable Pavement cross sections showing full and partial infiltration designs. Source: GVRD, 2005]]
 +
 
===Subgrade===
 
===Subgrade===
 
For infiltrating pavements, subgrade slopes should be minimized so that runoff will be able to infiltrate evenly through the entire surface. For steeply sloped sites (>5%), check dams, berms or weir structures on the native soils of the pavement should be considered. If the system is not designed for infiltration, the bottom should be sloped at 1 to 5% toward the underdrain. Subgrades should be compacted to 95% Standard Proctor Density.  If a lesser value is desired to promote infiltration, a thicker sub-base should be considered.  Subgrade soils should not be scarified.
 
For infiltrating pavements, subgrade slopes should be minimized so that runoff will be able to infiltrate evenly through the entire surface. For steeply sloped sites (>5%), check dams, berms or weir structures on the native soils of the pavement should be considered. If the system is not designed for infiltration, the bottom should be sloped at 1 to 5% toward the underdrain. Subgrades should be compacted to 95% Standard Proctor Density.  If a lesser value is desired to promote infiltration, a thicker sub-base should be considered.  Subgrade soils should not be scarified.
Line 66: Line 68:  
===Underdrain===
 
===Underdrain===
 
The diagram below displays permeable pavement cross sections showing full and partial infiltration designs.<ref>Greater Vancouver Regional District (GVRD). 2005. Stormwater Source Control Design Guidelines 2005. Prepared by Lanarc Consultants Limited, Kerr Wood Leidal Associates Limited and Goya Ngan. </ref> See [[Underdrains]] page for further guidance.  
 
The diagram below displays permeable pavement cross sections showing full and partial infiltration designs.<ref>Greater Vancouver Regional District (GVRD). 2005. Stormwater Source Control Design Guidelines 2005. Prepared by Lanarc Consultants Limited, Kerr Wood Leidal Associates Limited and Goya Ngan. </ref> See [[Underdrains]] page for further guidance.  
  −
  −
[[File:PermeablePaving CrossSection.png|thumb|550px|Permeable Pavement cross sections showing full and partial infiltration designs. Source: GVRD, 2005]]
      
===Access Structures===
 
===Access Structures===
Line 74: Line 73:     
===Overflow===
 
===Overflow===
[[File:OverflowEdge.png|thumb|Porous asphalt system with overflow edge draining to a reservoir. Source: Pennsylvania Department of Environmental Protection (PDEP). 2006.]]
  −
   
All designs require an overflow outlet connected to a storm sewer with capacity to convey larger storms. This is normally achieved with a catch basin outlet, but water may also be directed to a downstream practice (e.g. bioretention, swale). Another option is a gravel diaphragm or trench along the downgradient edge of the pavement that drains to the storage reservoir below.
 
All designs require an overflow outlet connected to a storm sewer with capacity to convey larger storms. This is normally achieved with a catch basin outlet, but water may also be directed to a downstream practice (e.g. bioretention, swale). Another option is a gravel diaphragm or trench along the downgradient edge of the pavement that drains to the storage reservoir below.
   Line 87: Line 84:     
===Foundation Aggregates===
 
===Foundation Aggregates===
 +
[[File:OverflowEdge.png|thumb|Porous asphalt system with overflow edge draining to a reservoir. Source: Pennsylvania Department of Environmental Protection (PDEP). 2006.]]
 +
 
All aggregates should meet the following criteria:
 
All aggregates should meet the following criteria:
 
* Porosity of 0.4
 
* Porosity of 0.4
Line 105: Line 104:     
For more information, also see [[Aggregates]] page.
 
For more information, also see [[Aggregates]] page.
 +
    
===Sizing Stone Reservoirs===
 
===Sizing Stone Reservoirs===

Navigation menu