The area required to settle the 1 mm particles is calculated as:
 
The area required to settle the 1 mm particles is calculated as:
 
:<math>A_{f}=120\times 0.1 = 12\ m^{2}</math>
 
:<math>A_{f}=120\times 0.1 = 12\ m^{2}</math>
So to meet the target particle removal, the forebay will be 12 m² in area. This gives the storage volume of 1.2 m³, which can be returned to the initial equation to determine the cleaning frequency as:
+
So to meet the target particle removal, the forebay will be 12 m² in area. This gives the storage volume of 1.8 m³, which can be returned to the initial equation to determine the cleaning frequency as:
:<math>C_{f}=\frac{1.2}{1.7\times 0.8\times 0.6}=\ almost\ 18\ months</math>
+
:<math>C_{f}=\frac{1.8}{1.7\times 0.8\times 0.6}=2.2\ years</math>
    