Starting with small-scale projects is a good strategy to increase public interest in LID practices, gauge municipal support, and gain retrofit experience. Small-scale projects include retrofitting your site with [[Landscape alternatives|landscape alternatives]], [[Rain barrels|rain barrels]], enhancements of existing swales, or using [[Pollution prevention|pollution prevention]] strategies and practices.
 
Starting with small-scale projects is a good strategy to increase public interest in LID practices, gauge municipal support, and gain retrofit experience. Small-scale projects include retrofitting your site with [[Landscape alternatives|landscape alternatives]], [[Rain barrels|rain barrels]], enhancements of existing swales, or using [[Pollution prevention|pollution prevention]] strategies and practices.
Line 18: Line 20:     
Due to less financial commitment, it can be easier to build colleague support and to gain supervisor approval for small-scale projects. However, small-scale projects like landscape alternatives and pollution prevention may not be easily identified as LID practices by the public. Your project team should consider establishing educational signage to inform the public.
 
Due to less financial commitment, it can be easier to build colleague support and to gain supervisor approval for small-scale projects. However, small-scale projects like landscape alternatives and pollution prevention may not be easily identified as LID practices by the public. Your project team should consider establishing educational signage to inform the public.
 +
 +
Pollution prevention (P2) projects are great small-scale projects for municipal facilities, such as schools and public works yards. Many P2 techniques and strategies do not require construction, consultants or contractors. In fact, simply adding signage to a site is a simple and easy to implement pollution prevention at municipal facilities.
 +
 +
A successful small-scale LID retrofit project is a good indication that you are ready to take on a more intensive retrofit project. You now know the resources that are available and understand the internal municipal processes required to move a LID project from planning to finished product.
    
===Large-scale projects===
 
===Large-scale projects===
Line 28: Line 34:  
* [[Bioswales]]
 
* [[Bioswales]]
 
* Perforated pipe systems
 
* Perforated pipe systems
* [[Permeable paving|Permeable pavement]]
+
* [[Permeable pavements]]
 
* [[Soakaways, Infiltration Trenches and Infiltration Chambers Guide|Soakaways]]
 
* [[Soakaways, Infiltration Trenches and Infiltration Chambers Guide|Soakaways]]
 
* [[Infiltration chambers]]
 
* [[Infiltration chambers]]
Line 54: Line 60:  
Consultants are required for large-scale retrofit projects, specifically for the final screening of options, pre-design, detailed design, tender and contract documents, construction supervision and administration, and assumption and verification. Site contractors are also required for large-scale LID retrofits.
 
Consultants are required for large-scale retrofit projects, specifically for the final screening of options, pre-design, detailed design, tender and contract documents, construction supervision and administration, and assumption and verification. Site contractors are also required for large-scale LID retrofits.
   −
Ideally, contractors should be pre-qualified based on previous experience with similar LID projects.
+
Ideally, contractors should be pre-qualified based on previous experience with similar LID projects. Remember, the contractor with the lowest bid does not necessarily deliver the best product.
    
====Intensive public consultation====
 
====Intensive public consultation====
Line 65: Line 71:     
==Parks==
 
==Parks==
 +
 
[[File:Example.jpg|thumb|The bioretention area installed at O’Connor Park in Mississauga is part of a stormwater management system that treats parking lot runoff prior to discharging to a local wetland. (Source: CVC)]]
 
[[File:Example.jpg|thumb|The bioretention area installed at O’Connor Park in Mississauga is part of a stormwater management system that treats parking lot runoff prior to discharging to a local wetland. (Source: CVC)]]
 
[[File:Example1.jpg|thumb|Urban parkettes may look small, but they have the potential to treat a large surface area of road. Typical ratios of impervious drainage area to a bioretention range from 5:1 to 15:1. (Source: CVC)]]
 
[[File:Example1.jpg|thumb|Urban parkettes may look small, but they have the potential to treat a large surface area of road. Typical ratios of impervious drainage area to a bioretention range from 5:1 to 15:1. (Source: CVC)]]
 
[[File:Example3.jpg|thumb|The road surface (left) contributes significantly more stormwater pollutants than the parkland area (right). To achieve maximum watershed benefit a designer could consider accepting runoff from this external area. (Source: CVC)]]
 
[[File:Example3.jpg|thumb|The road surface (left) contributes significantly more stormwater pollutants than the parkland area (right). To achieve maximum watershed benefit a designer could consider accepting runoff from this external area. (Source: CVC)]]
[[File:Example6.jpg|thumb|Source areas within a typical park]]
+
 
    
Parks range from simple parcels of municipal property to complex outdoor recreational facilities that include parking, sidewalks, trails, sports fields, field houses, operations facilities and washrooms. Each distinct area of your site can be a source for runoff (referred to as a ‘source area’). Target these areas when introducing LID in your park.
 
Parks range from simple parcels of municipal property to complex outdoor recreational facilities that include parking, sidewalks, trails, sports fields, field houses, operations facilities and washrooms. Each distinct area of your site can be a source for runoff (referred to as a ‘source area’). Target these areas when introducing LID in your park.
Line 78: Line 85:  
located adjacent to pervious areas such as lawns, gardens or naturalized areas. This makes parks an ideal location for a LID retrofit. Where grading allows, you can construct [[bioswales]] and [[bioretention]] areas in these green areas to pre-treat water prior to infiltration.
 
located adjacent to pervious areas such as lawns, gardens or naturalized areas. This makes parks an ideal location for a LID retrofit. Where grading allows, you can construct [[bioswales]] and [[bioretention]] areas in these green areas to pre-treat water prior to infiltration.
   −
You can also design parking surfaces and internal roadways as infiltration systems using permeable pavement. This retrofit strategy can be combined with other LID practices. Pathways paved with [[permeable paving]] are another LID option for your park. They reduce runoff volumes and encourage on-site infiltration. [[Exfiltration trenches]] are a viable option on many parks sites as well, as they provide an alternative to conventional conveyance systems (such as storm sewers). They encourage infiltration from hard surfaces and can be used to convey water to other LID features.
+
You can also design parking surfaces and internal roadways as infiltration systems using permeable pavement. This retrofit strategy can be combined with other LID practices. Pathways paved with [[permeable pavements]] are another LID option for your park. They reduce runoff volumes and encourage on-site infiltration. [[Exfiltration trenches]] are a viable option on many parks sites as well, as they provide an alternative to conventional conveyance systems (such as storm sewers). They encourage infiltration from hard surfaces and can be used to convey water to other LID features.
+
 
 
===Accepting drainage from off-site areas===   
 
===Accepting drainage from off-site areas===   
   Line 86: Line 93:     
===Inter-municipal transfer of funds===
 
===Inter-municipal transfer of funds===
 +
 
Integrating LID practices into the municipal stormwater management framework may require a change in how municipal funds are managed. Traditional stormwater management maintenance resources and funds may have to be transferred to a more landscape-based stormwater management maintenance program. Instead of infrequent but expensive stormwater management pond sediment removal operations, time and resources would be spent on more frequent but inexpensive maintenance projects, including pruning and weeding bioretention practices or sweeping permeable pavement.
 
Integrating LID practices into the municipal stormwater management framework may require a change in how municipal funds are managed. Traditional stormwater management maintenance resources and funds may have to be transferred to a more landscape-based stormwater management maintenance program. Instead of infrequent but expensive stormwater management pond sediment removal operations, time and resources would be spent on more frequent but inexpensive maintenance projects, including pruning and weeding bioretention practices or sweeping permeable pavement.
 
Municipalities generally have the required staff and infrastructure within departments (e.g. arborists and horticulturalists in parks departments) to manage the maintenance of LID measures. However, funding this maintenance may require a transfer of funding and additional training.  
 
Municipalities generally have the required staff and infrastructure within departments (e.g. arborists and horticulturalists in parks departments) to manage the maintenance of LID measures. However, funding this maintenance may require a transfer of funding and additional training.  
Line 92: Line 100:  
===Source Areas===   
 
===Source Areas===   
 
The best LID option for your site will depend what types of source areas are present. Source areas may include:
 
The best LID option for your site will depend what types of source areas are present. Source areas may include:
 +
[[File:Example6.jpg|thumb|Source areas within a typical park]]
 
* Active use areas
 
* Active use areas
 
* Passive use areas
 
* Passive use areas
Line 104: Line 113:  
|-
 
|-
 
!Source area
 
!Source area
![[Permeable paving]]
+
![[Permeable pavements]]
 
![[Bioretention]]
 
![[Bioretention]]
 
![[Enhanced grass swales]]
 
![[Enhanced grass swales]]
Line 124: Line 133:  
|}
 
|}
   −
===Making it happen: Approaches to getting LID into parks===
  −
The scale of your LID project will largely determine how to proceed. While you can usually complete small-scale LID projects with in-house expertise and resources, large-scale projects require external support from consultants and contractors.
  −
  −
====Small-scale projects====
  −
[[File:Example4.jpg|thumb|A [[no-mow]] zone is a landscape alternative that does not require construction activities. (Source: Aquafor Beech)]]
  −
  −
Starting with small-scale projects is a good strategy to increase public interest in LID practices, gauge municipal support and gain experience. Small-scale projects include retrofitting your park with landscape alternatives, rain barrels, or by using pollution prevention strategies and practices.
  −
  −
Small-scale projects require fewer resources and a smaller project budget:
  −
* They do not require integration into capital works projects
  −
* Engineering consultants are not required
  −
* Contractors may not be not required
  −
* External approvals are not required
  −
* Consultation with the public is limited
  −
  −
Due to less financial commitment, it can be easier to build colleague support and to gain supervisor approval for small-scale projects. However, small-scale projects like landscape alternatives and pollution prevention may not be easily identified as LID practices by the public. Your project team should consider establishing educational signage to inform the public.
  −
  −
====Large-scale projects====
   
[[File:Example5.jpg|thumb|When installing new parks equipment, consider whether the LID practices can be integrated into the design. Here a bioswale has been built into the landscape between a playground and sidewalk. (Source: CVC)]]
 
[[File:Example5.jpg|thumb|When installing new parks equipment, consider whether the LID practices can be integrated into the design. Here a bioswale has been built into the landscape between a playground and sidewalk. (Source: CVC)]]
  −
Large-scale projects require significantly more effort, budget, and staff than small-scale projects. Large-scale LID practices include:
  −
* [[Bioretention]]
  −
* [[Enhanced grass swales]]
  −
* [[Bioswales]]
  −
* Perforated pipe systems
  −
* [[Permeable paving|Permeable pavement]]
  −
* [[Soakaways, Infiltration Trenches and Infiltration Chambers Guide|Soakaways]]
  −
* [[Infiltration chambers]]
  −
* [[Rainwater harvesting]]
  −
* Prefabricated modules
  −
  −
Consider a large-scale project if your municipality or department would like to be a leader in sustainability. Large scale projects are often highly visible and attract more public attention. Large-scale projects may also be the only solution to site-specific challenges. For example, if the parking lot on your site does not have existing stormwater controls, small-scale projects are not likely to fully achieve compliance with water quality and quantity objectives. Consider using an infiltration chamber or bioswale project to meet those objectives.
  −
  −
Before starting a large-scale retrofit project, consider the following distinctions that set these retrofits apart from small-scale projects.
  −
  −
====Integration with capital works programs====
  −
Most large-scale LID retrofits must function with existing site infrastructure, such as storm sewers, catch basins and pavement systems. Constructing large-scale
  −
LID practices often requires these systems to be removed, exposed or replaced. Planned infrastructure replacement or rehabilitation projects provide opportunities for implementing LID practices. For example, if a planned project requires removing existing pavement, infiltration chambers, permeable pavement or bioretention can be incorporated. Budget and resources already set aside for infrastructure projects can be set aside for a retrofit project including replacement existing infrastructure.
  −
  −
====Involvement of consultants and contractors====
  −
Consultants are required for large-scale retrofit projects, specifically for the final screening of options, pre-design, detailed design, tender and contract documents, construction supervision and administration, and assumption and verification. Site contractors are also required for large-scale LID retrofits.
  −
  −
Ideally, contractors should be pre-qualified based on previous experience with similar LID projects.
  −
  −
====More intensive public consultation====
  −
Stakeholders must be closely involved in the retrofit process for large-scale LID projects. These projects have longer construction windows, may have significant impacts on long term public use patterns of the park, and will have significantly higher costs. Gaining public insight in advance of LID implementation can
  −
help address public concerns and information gaps, as well as identify public supporters and champions. Public consultation can help designers tailor the project to address community concerns and values.
  −
  −
====External approvals====
  −
Large-scale park retrofits may require a variety of approvals at the municipal, watershed, provincial and/or federal level. Since LID is still relatively new, you may encounter policies or bylaws that present barriers to LID retrofit projects. Alternatively, the municipality may have to enforce some policies and bylaws to facilitate the implementation of LID projects within parks.
      
[[Category:Planning]]
 
[[Category:Planning]]
Line 182: Line 142:     
==Schools==
 
==Schools==
 +
 
[[File:Elm Drive Bioretention.JPG|thumb|right|The Peel District School Board's Adult Education Centre South school partnered with the City of Mississauga to manage runoff from the adjacent street, Elm Drive, on their property. This partnership benefits the City by giving it space to provide an enhanced level of stormwater treatment, and benefited the school through the construction of new parking lay-bys for students. The site is maintained by the City of Mississauga. Source: CVC]]
 
[[File:Elm Drive Bioretention.JPG|thumb|right|The Peel District School Board's Adult Education Centre South school partnered with the City of Mississauga to manage runoff from the adjacent street, Elm Drive, on their property. This partnership benefits the City by giving it space to provide an enhanced level of stormwater treatment, and benefited the school through the construction of new parking lay-bys for students. The site is maintained by the City of Mississauga. Source: CVC]]
   Line 187: Line 148:  
(referred to as a ‘source area’). These areas should be
 
(referred to as a ‘source area’). These areas should be
 
targeted when introducing LID at your school.
 
targeted when introducing LID at your school.
 +
 
===Targeting hard surfaces===
 
===Targeting hard surfaces===
 +
 
Parking areas represent the most significant source of
 
Parking areas represent the most significant source of
 
pollutant loading from school sites and contribute significantly
 
pollutant loading from school sites and contribute significantly
Line 204: Line 167:  
integrated into the design. These practices will also function
 
integrated into the design. These practices will also function
 
to improve pedestrian safety and calm traffic.
 
to improve pedestrian safety and calm traffic.
 +
 
Other types of infiltrating practices like infiltration chambers
 
Other types of infiltrating practices like infiltration chambers
 
are gaining acceptance for their easy integration with parking
 
are gaining acceptance for their easy integration with parking
Line 214: Line 178:  
implement bioswales or bioretention areas. Perforated pipe
 
implement bioswales or bioretention areas. Perforated pipe
 
systems may also work in areas adjacent to parking lots.
 
systems may also work in areas adjacent to parking lots.
 +
 
===Roof options===
 
===Roof options===
 +
 
Schools typically have large flat roofs that produce a significant
 
Schools typically have large flat roofs that produce a significant
 
amount of runoff that is drained internally via rain leaders.
 
amount of runoff that is drained internally via rain leaders.
Line 233: Line 199:  
providing insulation during the winter and evaporative cooling
 
providing insulation during the winter and evaporative cooling
 
during the summer.
 
during the summer.
 +
 
===Pollution prevention (P2)===
 
===Pollution prevention (P2)===
 +
 
On school sites, [[Pollution prevention|P2 strategies and practices]], such as modifying
 
On school sites, [[Pollution prevention|P2 strategies and practices]], such as modifying
 
de-icing programs and isolating drainage from waste storage
 
de-icing programs and isolating drainage from waste storage
Line 241: Line 209:     
===School board partnerships with municipalities===
 
===School board partnerships with municipalities===
 +
 
LID practices located on school grounds can also be used to
 
LID practices located on school grounds can also be used to
 
treat stormwater from external properties. These partnership
 
treat stormwater from external properties. These partnership
Line 246: Line 215:  
Accepting and treating runoff on your existing property can
 
Accepting and treating runoff on your existing property can
 
make funds available through:
 
make funds available through:
Contributions to capital projects like parking lot
+
* Contributions to capital projects like parking lot rehabilitations which include rain gardens, permeable pavements, or subsurface infiltration facilities
rehabilitations which include rain gardens, permeable
+
* Ongoing revenues from long-term land leases to accommodate surface or subsurface LID retrofits
pavements, or subsurface infiltration facilities
+
* Funds for maintenance of on-site LIDs
Ongoing revenues from long-term land leases to
  −
accommodate surface or subsurface LID retrofits
  −
Funds for maintenance of on-site LIDs
     −
===Regulatory Compliance===
  −
The objectives, technologies, and standard practices
  −
associated with stormwater management are constantly
  −
evolving. It is unlikely that the stormwater management
  −
practices on your site meet modern industry standards.
  −
When you are making changes to your site, it is important to
  −
stay ahead of the regulations. Your school may not be required
  −
to improve on-site stormwater management infrastructure,
  −
but those retrofits can be beneficial and save money and time
  −
over the long term. Consider both current and future water
  −
regulations which may affect your property. Consulting with
  −
your municipality will help you determine if LID retrofits can
  −
reduce taxes or prevent costly upgrades required at a later
  −
date.
   
The table below identifies the LID practices that are common,
 
The table below identifies the LID practices that are common,
 
possible and unlikely options for the source areas that you
 
possible and unlikely options for the source areas that you
 
are likely to find on your school site. These source areas are:
 
are likely to find on your school site. These source areas are:
• Active use area
  −
• Passive use area
  −
• Pedestrian walkway
  −
• Internal driveway
  −
• Parking lot
  −
An aerial photo of a school property with each of these source
  −
areas accompanies Table 5.3.1. Options and implementation
  −
strategies for a few of these source areas will give you some
  −
ideas for your site.
  −
This guide provides two tiers of LID retrofit projects The scale
  −
of your LID retrofit project will largely determine how you will
  −
proceed with the retrofit process. You can usually complete
  −
small-scale LID projects with in-school expertise and
  −
resources. Large-scale projects will require external support
  −
from consultants and contractors.
  −
It is often difficult to ask students or teachers
  −
to maintain LID practices during the summer
  −
break. Include summer operations staff time in
  −
your budget during the planning process.
  −
===Small-scale projects===
  −
[[File:Fletchers Creek Senior School - planting - 2013.jpg|thumb|right|A student helps with planting at Fletchers Creek Senior School. Small-scale LID projects are a great way to engage with young children. Source: CVC]]
  −
Starting with small-scale projects is a good strategy to
  −
increase interest within your school, determine what support
  −
is available from stakeholder groups (parent council, school
  −
board, administration and operations) and gain retrofit
  −
experience. Small-scale projects include retrofitting your
  −
school property with landscape alternatives or rain barrels, or
  −
using pollution prevention strategies and practices.
  −
Small-scale projects require fewer resources and require a
  −
smaller project budget because:
  −
• They do not require integration into long-term
  −
infrastructure replacement and rehabilitation plans
  −
• Engineering consultants are not required
  −
• Contractors may not be required
  −
• External approvals are not required
  −
• Consultation with the public is limited
  −
Due to the smaller financial commitment, it can be easier
  −
to build colleague and school board support for small-scale
  −
projects.
  −
A successful small-scale LID retrofit project on your school
  −
property can be a good indication that you are ready to take on
  −
a more intensive retrofit project. You now know the resources
  −
that are available and understand the internal municipal
  −
processes required to move a LID project from planning to
  −
finished product.
  −
  −
===Large-scale projects===
  −
Large-scale projects require significantly more effort, budget,
  −
and staff than small-scale projects. Large-scale LID retrofits
  −
include:
  −
  −
* Bioretention
  −
* Enhanced grass swales
  −
* Bioswales
  −
* Perforated pipe systems
  −
* Permeable pavement
  −
* Soakaways
  −
* Infiltration chambers
  −
* Rainwater harvesting (excluding rain barrels)
  −
* Prefabricated modules
  −
* Green roofs
  −
  −
Consider a large-scale project if your school board is striving
  −
to be a leader in sustainability. Large-scale projects are often
  −
highly visible and attract more public attention. They may also
  −
be the only solution to site-specific challenges. For example, if
  −
the parking lot of your site does not have existing stormwater controls, small-scale projects are unlikely to fully achieve
  −
compliance with water quality and water quantity objectives.
  −
Instead, use a large-scale project like an infiltration chamber
  −
or bioswale.
  −
Before starting a large-scale retrofit project, consider the
  −
following distinctions that set these retrofits apart from small-scale
  −
projects.
  −
   
[[File:Landforms of a school.JPG|thumb|Source areas within a typical school site.]]
 
[[File:Landforms of a school.JPG|thumb|Source areas within a typical school site.]]
 +
* Active use area
 +
* Passive use area
 +
* Pedestrian walkway
 +
* Internal driveway
 +
* Parking lot
   −
===Integration with long-term infrastructure replacement and rehabilitation plans===
  −
Most large-scale LID retrofits must function with existing
  −
site infrastructure, such as storm sewers, catch basins,
  −
and pavement systems. The construction of large-scale
  −
LID practices often requires these systems to be removed,
  −
exposed, or replaced. The best time for this type of project to
  −
occur is when an infrastructure replacement or rehabilitation
  −
project is already planned.
  −
Like other large public sites, schools typically have maintenance
  −
programs that take into consideration the expected life cycle
  −
of critical site components, including parking lots and roofs.
  −
To save construction costs, incorporate LID retrofits into
  −
these projects and share construction material, construction
  −
equipment, staff resources, and time.
  −
For example, installing bioretention, infiltration chambers,
  −
or permeable pavement in a parking lot will require the
  −
existing pavement to be removed. Budget and resources that
  −
have been set aside for a parking lot replacement could be
  −
transferred to a retrofit project.
     −
===Involvement of consultants and contractors===
+
See the landforms of a school picture on the right for ideas on how to target these areas. The table below gives a more detailed breakdown of LID options for different source areas.
Consultants are required for large-scale retrofit projects,
  −
specifically for the final screening of options, pre-design,
  −
detailed design, tender and contract documents, construction
  −
supervision and administration, and assumption and
  −
verification. The consultant selection process is described in
  −
Chapter 7.
  −
Site contractors are also required for large-scale LID retrofits.
  −
Contractors should be pre-qualified based on previous
  −
experience with similar LID projects.
  −
Remember, the contractor with the lowest bid
  −
does not necessarily deliver the best product.
  −
Refer to Chapter 7 for tips on how to select the
  −
right contractor for your project.
  −
===More intensive public consultation===
  −
Stakeholders must be closely involved in the retrofit process
  −
for large-scale LID projects. These projects have longer
  −
construction windows, larger costs, and will more significantly
  −
affect the use patterns of the property. Large-scale projects
  −
are also more complex systems that require continued
  −
inspections, operations, and maintenance to achieve
  −
continued success. All stakeholder groups must be aware of
  −
the long-term project needs before implementation.
  −
===External approvals===
  −
Large-scale retrofits may require a variety of approvals at the
  −
municipal, watershed, provincial, and/or federal level.
  −
Since LID is still relatively new, you may encounter policies or
  −
bylaws that present barriers to LID retrofit projects. Conduct a
  −
review of relevant municipal and school board policies prior to
  −
implementing a large-scale retrofit. School board policies may
  −
require amendments to move forward.
  −
===Next Steps===
  −
After reading this section you should know how to select the
  −
right LID practice for your site. You should also be familiar
  −
with the details you need to consider before undertaking an
  −
LID retrofit.
  −
For further guidance on implementing and constructing LID
  −
practices, '''please refer to Chapters 7-9.''' These chapters
  −
provides the next steps for you to implement your LID project,
  −
including building the project team, creating a design,
  −
getting approvals, construction, certification and guidance on
  −
operations and maintenance of LID practices.
      
{| class="wikitable sortable" style="text-align: center;"
 
{| class="wikitable sortable" style="text-align: center;"
Line 413: Line 236:  
(** = Common, * = Possible, o = Unusual)
 
(** = Common, * = Possible, o = Unusual)
 
! Source area  
 
! Source area  
! [[Permeable pavement]]  
+
! [[Permeable pavements]]  
 
! [[Bioretention]]  
 
! [[Bioretention]]  
 
! [[Enhanced grass swales]] / [[Bioswales|bioswales]]  
 
! [[Enhanced grass swales]] / [[Bioswales|bioswales]]  
 
! [[Green roofs]]  
 
! [[Green roofs]]  
![[Soakaways, Infiltration Trenches and Infiltration Chambers Guide| Soakaways]] and [[Infiltration trenches|infiltration trenches]]  
+
! Soakaways and [[Infiltration trenches|infiltration trenches]]  
 
! [[Exfiltration trenches|Perforated pipe systems]]  
 
! [[Exfiltration trenches|Perforated pipe systems]]  
 
! [[Rainwater harvesting]]  
 
! [[Rainwater harvesting]]  
Line 438: Line 261:     
==Places of worship==
 
==Places of worship==
[[File:Landforms of a place of worship.JPG|thumb|Source areas within a typical place of worship]]
     −
Each distinct area of your site can be a source for runoff
+
Each distinct area of a place of worship can be a source for runoff
 
(referred to as a ‘source area’). One or more of these areas
 
(referred to as a ‘source area’). One or more of these areas
 
should be targeted when introducing LID at your place of
 
should be targeted when introducing LID at your place of
Line 468: Line 290:  
over 30 years, and permeable interlocking concrete pavers
 
over 30 years, and permeable interlocking concrete pavers
 
can have a design life of 20 to 25 years or greater.
 
can have a design life of 20 to 25 years or greater.
 +
 +
Prefabricated modular infiltration chambers are gaining
 +
acceptance because they are easy to integrate with parking
 +
lot functions. These subsurface systems are typically installed
 +
over a coarse granular reservoir to provide water storage and
 +
allow infiltration into native soils. Infiltration chambers under
 +
conventional asphalt systems work well on sites where parking
 +
demand does not allow space for a stormwater feature.
 +
 
Using LID techniques to manage stormwater can also
 
Using LID techniques to manage stormwater can also
 
eliminate or reduce the need for an on-site storm sewer
 
eliminate or reduce the need for an on-site storm sewer
Line 475: Line 306:  
negates the need to replace on-site piping, thereby saving
 
negates the need to replace on-site piping, thereby saving
 
long-term infrastructure replacement costs.
 
long-term infrastructure replacement costs.
Prefabricated modular infiltration chambers are gaining
  −
acceptance because they are easy to integrate with parking
  −
lot functions. These subsurface systems are typically installed
  −
over a coarse granular reservoir to provide water storage and
  −
allow infiltration into native soils. Infiltration chambers under
  −
conventional asphalt systems work well on sites where parking
  −
demand does not allow space for a stormwater feature.
      
===Landscaped areas===
 
===Landscaped areas===
Line 499: Line 323:  
this way, it can be easy to integrate harvesting systems into
 
this way, it can be easy to integrate harvesting systems into
 
the landscape surrounding your building.
 
the landscape surrounding your building.
 +
 
Roof runoff can also be directed to soakaways located on
 
Roof runoff can also be directed to soakaways located on
 
passive use areas around your building. Due to the relatively
 
passive use areas around your building. Due to the relatively
Line 507: Line 332:  
The LID option that best fits your site will depend what types
 
The LID option that best fits your site will depend what types
 
of source areas are present. Types of source areas include:
 
of source areas are present. Types of source areas include:
 +
[[File:Landforms of a place of worship.JPG|thumb|Source areas within a typical place of worship]]
 
* Active use area
 
* Active use area
 
* Passive use area
 
* Passive use area
Line 513: Line 339:  
* Parking lot
 
* Parking lot
   −
On park sites, pollution prevention is often associated with
+
At places of worship, pollution prevention is often associated with
 
changes to operations and maintenance practices and has
 
changes to operations and maintenance practices and has
not been included in Table 6.3.1. An aerial photo of a park
+
not been included in the table below.  
with each of these source areas accompanies Table 6.3.1.
  −
Options and implementation strategies for a few of these
  −
source areas will give you some ideas for your park site.
  −
 
  −
The scale
  −
of your LID retrofit project will largely determine how you will
  −
proceed. You can usually complete
  −
small-scale LID projects with in-house expertise and
  −
resources. Large-scale projects will require external support
  −
from consultants and contractors.
  −
 
  −
===Small-scale projects===
  −
 
  −
Starting with small-scale projects is a good strategy to
  −
increase interest within your community, determine if
  −
support is available from stakeholder groups and gain retrofit
  −
experience. Small-scale projects include retrofitting your
  −
property with landscape alternatives, rain barrels or using
  −
pollution prevention strategies and practices.
  −
 
  −
Small-scale projects require few resources and a
  −
small project budget because:
  −
* They do not require integration into capital works projects
  −
* Engineering consultants are not required
  −
* Contractors are not required
  −
* External approvals are not required
  −
* Consultation with the public is limited
  −
Due to the less significant financial commitment, it can be
  −
easier to build the case for support for small-scale projects.
  −
A successful small-scale LID retrofit project on your property
  −
is a good indication that you are ready to take on a more
  −
intensive retrofit project. You now know the resources that Large-scale projects
  −
Large-scale projects require significantly more effort, budget,
  −
and staff than small-scale projects. Large-scale LID retrofits
  −
include:
  −
* Bioretention
  −
* Enhanced grass swales
  −
* Bioswales
  −
* Perforated pipe systems
  −
* Permeable pavement
  −
* Soakaways
  −
* Infiltration chambers
  −
* Rainwater harvesting (excluding rain barrels)
  −
* Prefabricated modules
  −
* Green roofs
  −
 
  −
Consider a large-scale project if your place of worship is
  −
striving to be a community leader in sustainability. Large-scale
  −
projects are often highly visible and attract more public
  −
attention. They may also be the only solution
  −
to site-specific challenges, like poor drainage. Before starting
  −
a large-scale retrofit project consider the distinctions that set
  −
these retrofits apart from small-scale projects.
  −
 
  −
===Integration with long-term infrastructure replacement and rehabilitation plans===
  −
 
  −
Most large-scale LID retrofits must function with existing
  −
site infrastructure, such as storm sewers, catch basins,
  −
and pavement systems. The construction of large-scale
  −
LID practices often requires these systems to be removed,
  −
exposed, or replaced. The best time for this type of project is when an infrastructure replacement or rehabilitation
  −
project is already planned.
  −
Maintenance programs and budgets that take into consideration
  −
the expected life cycle of critical site components, including
  −
parking lot and roofs, are valuable resources for large-scale
  −
projects. If the replacement of these features is forecasted in
  −
your site budget well in advance, asses if it is advantageous
  −
to incorporate LID retrofits into these projects. Remember,
  −
sharing construction materials, construction equipment, staff
  −
resources, and time will reduce the budget for your retrofit.
  −
For example, installing bioretention, infiltration chambers,
  −
or permeable pavement in a parking lot will require the
  −
existing pavement to be removed. Budget and resources that
  −
have been set aside for a parking lot replacement could be
  −
transferred to the LID retrofit project.
  −
 
  −
===Involvement of consultants and contractors===
  −
 
  −
Consultants are required for large-scale retrofit projects,
  −
specifically for the final screening of options, pre-design,
  −
detailed design, tender and contract documents, construction
  −
supervision and administration, and assumption and
  −
verification.
  −
 
  −
Site contractors are also required for large-scale LID retrofits.
  −
Contractors should be pre-qualified based on previous
  −
experience with similar LID projects.
  −
 
  −
External approvals
  −
Large-scale retrofits may require a variety of approvals at the
  −
municipal, watershed, provincial, and/or federal level.
  −
Since LID is still relatively new, you may encounter policies
  −
or bylaws that present barriers to LID retrofit projects.
  −
Alternatively, the municipality may have to amend or enforce
  −
some policies and bylaws to facilitate the implementation of
  −
LID projects on your site.
      
{| class="wikitable sortable" style="text-align: center;"
 
{| class="wikitable sortable" style="text-align: center;"
Line 617: Line 347:  
(** = Common, * = Possible, o = Unusual)
 
(** = Common, * = Possible, o = Unusual)
 
! Source area  
 
! Source area  
! [[Permeable pavement]]  
+
! [[Permeable pavements]]  
 
! [[Bioretention]]  
 
! [[Bioretention]]  
 
! [[Enhanced grass swales]] / [[Bioswales|bioswales]]  
 
! [[Enhanced grass swales]] / [[Bioswales|bioswales]]  
 
! [[Green roofs]]  
 
! [[Green roofs]]  
![[Soakaways, Infiltration Trenches and Infiltration Chambers Guide| Soakaways]] and [[Infiltration trenches|infiltration trenches]]  
+
! Soakaways and [[Infiltration chambers|infiltration chambers]]  
 
! [[Exfiltration trenches|Perforated pipe systems]]  
 
! [[Exfiltration trenches|Perforated pipe systems]]  
 
! [[Rainwater harvesting]]  
 
! [[Rainwater harvesting]]  
Line 640: Line 370:  
|style="text-align: left;" |Building || * || * || * || ** || ** || * || ** || o || o || *
 
|style="text-align: left;" |Building || * || * || * || ** || ** || * || ** || o || o || *
 
|}
 
|}
  −
===stuff to maybe integrate into the above===
  −
  −
'''Figure 6.3.1: When considering any parking lot retrofit, first determine if the parking spaces provided are consistent with the'''
  −
demand. In place of worship, the demand will fluctuate. (Source: CVC)
  −
  −
'''Did you know that green roofs can help'''
  −
reduce your heating and cooling costs?
  −
These systems absorb heat and act as
  −
insulators for buildings. It has been estimated
  −
that a 3,000 m2 green roof on a one story
  −
building in Toronto could reduce the cost of
  −
cooling a building in the summer by 6% and
  −
the cost of heating a building by 10% in the
  −
winter23.
      