Design and operation and maintenance program assumptions used to generate cost estimates are based on tool default values and the following STEP recommendations:
 
Design and operation and maintenance program assumptions used to generate cost estimates are based on tool default values and the following STEP recommendations:
* Native soil infiltration rates for Full, and Partial Infiltration Design scenarios were assumed to be 20 mm/h and 10 mm/h respectively, and a safety factor of 2.5 was applied to calculate the design infiltration rate.  
+
* Native soil infiltration rates for Full Infiltration Design scenarios were assumed to be 20 mm/h, and a safety factor of 2.5 was applied to calculate the design infiltration rate.  
 
* Operation and maintenance (O&M) cost estimates assume annual inspections, removal of trash and debris twice a year, and removal of sediment from pretreatment structures annually. Verification inspections are included every 5 years to confirm adequate maintenance, and every 15 years to confirm adequate drainage performance through in-situ chamber system water level monitoring during natural storm events.
 
* Operation and maintenance (O&M) cost estimates assume annual inspections, removal of trash and debris twice a year, and removal of sediment from pretreatment structures annually. Verification inspections are included every 5 years to confirm adequate maintenance, and every 15 years to confirm adequate drainage performance through in-situ chamber system water level monitoring during natural storm events.
 
* Infiltration chamber system length of 5 metres and composed of 22 chambers in total.
 
* Infiltration chamber system length of 5 metres and composed of 22 chambers in total.
Line 21: Line 21:     
===Notes===
 
===Notes===
* Designs include [[pretreatment]] through hydrodynamic separator ([[Oil and Grit Separator| i.e., oil and grit separator]]) and isolated chamber row.
+
* Design include [[pretreatment]] through hydrodynamic separator ([[Oil and Grit Separator| i.e., oil and grit separator]]) and isolated chamber row.
 
* The tool calculates costs for new (greenfield) development contexts and includes costs for contractor overhead and profit, material, delivery, labour, equipment (rental, operating and operator costs), hauling and disposal.  
 
* The tool calculates costs for new (greenfield) development contexts and includes costs for contractor overhead and profit, material, delivery, labour, equipment (rental, operating and operator costs), hauling and disposal.  
 
** Land value and equipment mobilization and demobilization costs are not included, assuming BMP construction is part of overall development site construction.
 
** Land value and equipment mobilization and demobilization costs are not included, assuming BMP construction is part of overall development site construction.
Line 33: Line 33:  
==Construction Costs==
 
==Construction Costs==
   −
[[File:ConstructionTable InfilChamb Full Infil.PNG|thumb|left|610px|'''Construction Costs Per Unit Drainage Area (CAD$/m<sup>2</sup>) - Full Infiltration Design, 25 mm Retention''']]
+
[[File:ConstructionTable InfilChamb Full Infil 2023.PNG|thumb|center|900px|'''Construction Costs Per Unit Drainage Area (CAD$/m<sup>2</sup>) - Full Infiltration Design, 25 mm Retention''']]<br>
   −
[[File:ConstructionTable InfilChamb Partial Infil.PNG|thumb|center|615px|'''Construction Costs Per Unit Drainage Area (CAD$/m<sup>2</sup>) - Partial Infiltration Design, 25 mm Retention''']]
+
<small>'''Note:''' Click on image to enlarge to view associated construction cost estimates.</small><br>
 
  −
 
  −
<small>'''Note:''' Click on each image to enlarge to view associated construction cost estimates.</small><br>
  −
 
  −
 
  −
Above you can find breakdowns of construction costs by expense type for each infiltration chamber system design scenario:
  −
#[[Infiltration chambers|Infiltration Chamber: Full Infiltration]]
  −
#[[Infiltration chambers|Infiltration Chamber: Partial Infiltration]]
      +
Above you can find a breakdown of construction costs by expense type.<br>
 +
<br>
 
As can be seen, regardless of design configuration, Material & Installation expenses represent the largest portion of total construction costs (75%).
 
As can be seen, regardless of design configuration, Material & Installation expenses represent the largest portion of total construction costs (75%).
    
==Life Cycle Costs==
 
==Life Cycle Costs==
Below are capital and life cycle cost estimates for the two [[Infiltration chambers|infiltration chamber]] design scenarios over 25- and 50-year time periods. The estimates of maintenance and rehabilitation (life cycle) costs represent net present values. Operation and maintenance costs are predicted to represent 37% of total life cycle costs over the 25-year evaluation period, and increase to 49% of total life cycle costs over the 50-year period, due to cost associated with removal of sediment from the isolated chamber row pretreatment devices every 8 years.
+
Below are capital and life cycle cost estimates for the [[Infiltration chambers|infiltration chamber]] design scenario over 25- and 50-year time periods. The estimate of maintenance and rehabilitation (life cycle) cost represents net present values. Operation and maintenance costs are predicted to represent 37% of total life cycle costs over the 25-year evaluation period, and increase to 49% of total life cycle costs over the 50-year period, due to cost associated with removal of sediment from the isolated chamber row pretreatment devices every 8 years.
 
      
===25-Year life cycle cost break down===
 
===25-Year life cycle cost break down===
   −
[[File:25yr LCCT InfilChamb Full Infil.PNG|thumb|left|615px|'''Infiltration Trench: Full Infiltration''']]
+
[[File:25yr LCCT InfilChamb Full Infil 2023.PNG|thumb|center|900px|'''Infiltration Trench: Full Infiltration''']]<br>
   −
[[File:25yr LCCT InfilChamb Partial Infil.PNG|thumb|center|615px|'''Infiltration Trench: Partial Infiltration''']]
+
<small>'''Note:''' Click on image to enlarge to view associated life cycle cost estimate.</small><br>
 
+
</br>
 
  −
<small>'''Note:''' Click on each image to enlarge to view associated life cycle cost estimate.</small><br>
      
===50-Year life cycle cost break down===
 
===50-Year life cycle cost break down===
   −
[[File:50yr LCCT InfilChamb Full Infil.PNG|thumb|left|615px|'''Infiltration Chamber: Full Infiltration''']]
+
[[File:50yr LCCT InfilChamb Full Infil 2023.PNG|thumb|center|900px|'''Infiltration Chamber: Full Infiltration''']]<br>
 
  −
[[File:50yr LCCT InfilChamb Partial Infil.PNG|thumb|center|615px|'''Infiltration Chamber: Partial Infiltration''']]
  −
 
     −
<small>'''Note:''' Click on each image to enlarge to view associated life cycle cost estimate.</small><br>
+
<small>'''Note:''' Click on image to enlarge to view associated life cycle cost estimate.</small><br>
    
==Cost Summary Tables==
 
==Cost Summary Tables==
Total life cycle cost estimates for the two [[Infiltration chambers|infiltration chamber]] configurations are the same with the total being ($120,218.83).<br>
+
Total life cycle cost estimate over the 50 year evaluation period for [[Infiltration chambers|infiltration chamber system]] on highly permeable native soil design scenario is $123,670.89.<br>
    
===Full Infiltration===
 
===Full Infiltration===
[[File:East Gwillimbury.png|800px|thumb|Example of "crate style" [[Infiltration chambers]] being installed in East Gwillimbury. Photo credit: [https://www.makeway.ca/products/stormwater-management-systems/ Make-Way Environmental Technologies Inc.]]
+
[[File:East Gwillimbury.png|400px|thumb|Example of "crate style" [[Infiltration chambers]] being installed in East Gwillimbury. Photo credit: [https://www.makeway.ca/products/stormwater-management-systems/ Make-Way Environmental Technologies Inc.]]
   −
[[File:Design Table InfilChamb Full Infil.PNG|700px]]<br>
+
[[File:Design Table InfilChamb Full Infil 2023.PNG|830px]]<br>
 
</br>
 
</br>
===Partial Infiltration===
  −
[[File:Design Table InfilChamb Partial Infil.PNG|700px]]<br>
   
</br>
 
</br>
    