Line 11: |
Line 11: |
| | | |
| Design and operation and maintenance program assumptions used to generate cost estimates are based on tool default values and the following STEP recommendations: | | Design and operation and maintenance program assumptions used to generate cost estimates are based on tool default values and the following STEP recommendations: |
− | * Native soil infiltration rate for Full Infiltration Design scenario was assumed to be 20 mm/h, and a safety factor of 2.5 was applied to calculate the design infiltration rate. | + | * Native soil infiltration rate for Full Infiltration Design scenario was assumed to be 20 mm/h, and a safety factor of 2.5 was applied to calculate the design infiltration rate. |
− | * Operation and maintenance (O&M) cost estimates assume annual inspections, removal of trash and debris twice a year, removal of sediment from outlet catch basin annually, and removal of weeds twice a year. Verification inspections are included every 5 years to confirm adequate maintenance, and every 15 years to confirm adequate drainage performance through in-situ surface infiltration rate testing. | + | * Ditch inlet catch basin structure located at furthest downgradient end, with connection to storm sewer pipe, included as the outlet. |
| + | * Operation and maintenance (O&M) cost estimates assume annual inspections, removal of trash and debris twice a year, removal of sediment from curb inlets and outlet catch basin annually, and removal of weeds twice a year. Verification inspections are included every 5 years to confirm adequate maintenance, and every 15 years to confirm adequate drainage performance through in-situ surface infiltration rate testing. |
| * Impervious drainage area to pervious swale footprint area of 10:1 (tool default value). | | * Impervious drainage area to pervious swale footprint area of 10:1 (tool default value). |
| * Designed with a trapezoidal cross section with a top width of 4.75 m, bottom width of 0.75 m, and 2.5:1 side slopes (tool default values). | | * Designed with a trapezoidal cross section with a top width of 4.75 m, bottom width of 0.75 m, and 2.5:1 side slopes (tool default values). |
Line 35: |
Line 36: |
| ==Construction Costs== | | ==Construction Costs== |
| | | |
− | [[File:Construction Breakdown EnhancedSwales Full Infil.PNG|thumb|center|950px|'''Construction Costs Per Unit Drainage Area (CAD$/m<sup>2</sup>) - Full Infiltration Design, 25 mm Treatment''']] | + | [[File:Construction Breakdown EnhancedSwales Full Infil 2023.PNG|thumb|center|950px|'''Construction Costs Per Unit Drainage Area (CAD$/m<sup>2</sup>) - Full Infiltration Design, 25 mm Treatment''']] |
| | | |
| | | |
Line 51: |
Line 52: |
| ===25-Year life cycle cost break down=== | | ===25-Year life cycle cost break down=== |
| | | |
− | [[File:25yr LCCT EnhancedSwales Full Infil.PNG|thumb|center|900px|'''Enhanced Swales: Full Infiltration''']] | + | [[File:25yr LCCT EnhancedSwales Full Infil 2023.PNG|thumb|center|900px|'''Enhanced Swales: Full Infiltration''']] |
| | | |
| <small>'''Note:''' Click on each image to enlarge to view associated life cycle cost estimate.</small><br> | | <small>'''Note:''' Click on each image to enlarge to view associated life cycle cost estimate.</small><br> |
| + | </br> |
| | | |
| ===50-Year life cycle cost break down=== | | ===50-Year life cycle cost break down=== |
| | | |
− | [[File:50yr LCCT EnhancedSwales Full Infil.PNG|thumb|center|900px|'''Enhanced Swales: Full Infiltration''']] | + | [[File:50yr LCCT EnhancedSwales Full Infil 2023.PNG|thumb|center|900px|'''Enhanced Swales: Full Infiltration''']] |
| | | |
| <small>'''Note:''' Click on each image to enlarge to view associated life cycle cost estimate.</small><br> | | <small>'''Note:''' Click on each image to enlarge to view associated life cycle cost estimate.</small><br> |
| + | </br> |
| | | |
| ==Cost Summary Tables== | | ==Cost Summary Tables== |
Line 65: |
Line 68: |
| | | |
| ===Full Infiltration=== | | ===Full Infiltration=== |
− | [[File:CVC Office, Grass Swale.JPG|500px|thumb|Enhanced Grass [[swale]] in CVC headquarters parking lot, Mississauga ON.]] | + | [[File:CVC Office, Grass Swale.JPG|650px|thumb|Enhanced Grass [[swale]] in CVC headquarters parking lot, Mississauga ON.]] |
| | | |
− | [[File:Design Table EnhancedSwales Full Infil.PNG|700px]]<br> | + | [[File:Design Table EnhancedSwales Full Infil 2023.PNG|700px]]<br> |
| </br> | | </br> |