Enhanced Swales: Life Cycle Costs
Overview[edit]
Enhanced swales (also referred to as Enhanced Grass Swales - EGS) are vegetated open channels designed to convey, treat and attenuate stormwater runoff. Simple grass channels or ditches have long been used for stormwater conveyance, particularly for road drainage. Enhanced swales incorporate design features such as modified geometry and check dams that improve the contaminant removal and runoff reduction functions of simple grass channel and roadside ditch designs. Where development density, topography and depth to water table permit, swales are a preferable alternative to curb and gutter and storm drains as a stormwater conveyance system. STEP has prepared life cycle costs estimates for an enhanced swale located on highly permeable native soil (Full Infiltration design), based on a 2,000 m2 road drainage area, runoff control target of 25 mm depth and 72 hour drainage period, which can be viewed below. To generate your own life cycle cost estimates customized to the development context, design criteria, and constraints applicable to your site, access the updated LID Life Cycle Costing Tool (LCCT) here.
Design Assumptions[edit]
Enhanced grass swales (EGS) are an ideal technology for sloped sites and cheaply retrofitting and improving the performance of existing grass swales. Components include: graded channel, resilient turf grass or other planting, check dams to facilitate short term ponding. Additional components include, amended soil or filter media to increase infiltration to soils below, and turf reinforcement to prevent scour. Swales can provide pretreatment for other BMPs (bioretention, soakaways, exfiltration trenches) or be designed in series with other practices as part of a treatment train.
Design and operation and maintenance program assumptions used to generate cost estimates are based on tool default values and the following STEP recommendations:
- Native soil infiltration rate for Full Infiltration Design scenario was assumed to be 20 mm/h, and a safety factor of 2.5 was applied to calculate the design infiltration rate.
- Operation and maintenance (O&M) cost estimates assume annual inspections, removal of trash and debris twice a year, removal of sediment from pretreatment structures annually, and removal of weeds twice a year (where applicable). Verification inspections are included every 5 years to confirm adequate maintenance, and every 15 years to confirm adequate drainage performance through in-situ surface infiltration rate testing (where applicable)
- Designed with a trapezoidal or triangular cross section.
- Length between culverts should be 5 meters or greater.
- Designed with a bottom width between 0.6-2.4 m (allows shallow flows and adequate water treatment).
- Longitudinal slope should be between 0.5 and 4%. Check dams should be incorporated on slopes greater than 3%.
- Side slopes should be flat to aid in providing pre-treatment for lateral incoming flows and maximize swale filtering surface.
- Steeper side slopes may be susceptible to erosion from incoming lateral flows. A maximum slope of 2.5:1 is recommended (Tool default).
- Maximum flow depth should be 50% of grass height for regularly mown swales, to maximum of 75 mm.
- For infrequently mown swales, STEP recommends maximum flows of 33% of vegetation height.
- Designed for a maximum velocity of 0.3 m/s.
- Convey locally required design storm (~10 mm year storm) at non-erosive velocities.
Notes[edit]
- The Tool assumes an in-line system.
- The Tool assumed curb-and-gutter around the circumference of the facility with curb-cut inlets every 6 to 0.5 meter squared and stone splash pads.
- The greater the slope, the more check dams placed by the Tool. The unit cost for check dams is for the amount of material required, not number of dams.
- If configuration include driveway (2 laned), a culvert pipe connects the enhanced grass swale (EGS) and an extra 0.1m of gravel is added beneath culvert.
- Swales which cross multiple driveways or smaller driveways can be accounted for by multiplying or dividing these costs in the "Additional Costs" cells.
- The tool calculates costs for new (greenfield) development contexts and includes costs for contractor overhead and profit, material, delivery, labour, equipment (rental, operating and operator costs), hauling and disposal.
- Land value and equipment mobilization and demobilization costs are not included, assuming BMP construction is part of overall development site construction.
- Design and Engineering cost estimates are not calculated by the tool and must be supplied by the user.
- The tool adds 10% contingency and additional overhead as default.
- All cost estimates are in Canadian dollars and represent the net present value (NPV) as the tool takes into account average annual interest and discount rates over the 25 and 50 year operating life cycle periods.
- Unit costs are based on 2018 RSMeans standard union pricing.
- Additional costs associated with retrofit or redevelopment contexts is assumed to be 16% of the cost estimate for new (greenfield) construction contexts.
- Retrofit construction cost estimates are included in the 'Costs Summary' section for comparison.
- Retrofit construction cost estimates are included in the 'Costs Summary' section for comparison.
Construction Costs[edit]
Note: Please click on each image to enlarge to view associated construction cost estimates.
Above you can find a cost breakdown of a 1000m2 LID configuration:
Material & Installation expenses represent the largest portion of total construction costs (50%).
Life Cycle Costs[edit]
Below are capital and life cycle cost estimates for the Enhanced swales Full Infiltration configuration over 25- and 50-year time periods. The estimates of maintenance and rehabilitation (life cycle) costs represent net present values. Operation and maintenance costs are predicted to represent 45% of total life cycle costs over the 25-year evaluation period, and increase to 59% of total life cycle costs over the 50-year period, due to increased levels of litter removal, watering (establishment period - years 1 & 2 / annually and / drought watering) cleaning out and vacuuming of the catchbasin, mowing, replacement of sod, weeding and pruning of the BMP's planted vegetation.
25-Year life cycle cost break down[edit]
Note: Click on each image to enlarge to view associated life cycle cost estimate.
50-Year life cycle cost break down[edit]
Note: Click on each image to enlarge to view associated life cycle cost estimate.
Cost Summary Tables[edit]
Total life cycle cost estimates for the Enhanced swale Full Infiltration design configuration is ($23,451.36), makign it one of the cheapest LID BMP options.