| Peak Flow Reduction || Percent reduction of the 100-year post development flow to pre-development conditions of the site || Up to 40% ||rowspan="4" style="background:; color:black"| To a total of no more than 50%
−
|-
−
| Water Quality Treatment || Consistent with Provincial criteria for enhanced treatment || Up to 10%
−
|-
−
| Runoff Volume Reduction || Percent capture of first 15 mm of rainfall during a single rainfall event || Up to 15%
−
|-
−
| Pollution Prevention || Develop and implement a pollution prevention plan || Up to 5%
−
|}
−
A maximum of 50% credit can be achieved by a property owner or operator. The 50% cap reflects the
−
maximum proportion of the City’s stormwater program in terms of cost that may be beneficially
−
impacted by on-site BMPs. The balance of the City’s program requires funding regardless of BMPs that