Line 46: Line 46:     
==Large stone and riprap==
 
==Large stone and riprap==
{{:Construction: large stone and riprap}}
+
Riprap serves as a protective layer to: prevent sediment entering the underlying layers and clogging the LID facility, dissipate stormwater energy, and stabilize the terrain and slope.
 +
 
 +
'''Construction Steps:'''
 +
#Backfill the material from the outside of the LID facility to avoid compaction.
 +
#Ensure the material is being placed to the elevation and thickness to the design requirements.
 +
 
 +
'''Key Inspection Points:'''
 +
*Arrival of material to the site: material meets specifications as per design, no debris in the aggregate and, if possible, washed or clean stone with little to no fine materials in it.
 +
*Placement: material is backfilled to the right depth and elevation.
 +
 
 +
'''Common Mistakes to Avoid:'''
 +
*Use of wrong material that does not meet design specifications. If there are changes in the material, it must be approved by the supervisor or project manager.<br> 
 +
[[Riprap: Gallery|Riprap]]
    
==Plant material verification and installation==
 
==Plant material verification and installation==