As the maximum flow rate exceeds the downstream maximum permissible flow, the design must be amended. In order of preference, some options include:
 
As the maximum flow rate exceeds the downstream maximum permissible flow, the design must be amended. In order of preference, some options include:
 
#Increasing the size of the downstream pipe to accommodate a greater flow rate;
 
#Increasing the size of the downstream pipe to accommodate a greater flow rate;
#Reducing the depth of the filter media bed in agreement with a Landscape Architect, and increasing pretreatment (as filter bed < 600 mmm will provide less treatment); or   
+
#Reducing the depth of the filter media bed in agreement with a Landscape Architect, and increasing pretreatment (as filter bed < 600 mm deep will provide less water quality treatment); or   
 
#Reformulating the bioretention filter media in collaboration with the soils provider, to reduce the hydraulic conductivity.
 
#Reformulating the bioretention filter media in collaboration with the soils provider, to reduce the hydraulic conductivity.