CLI-ECA
Overview[edit]
The Municipal Consolidated Linear Infrastructure Environmental Compliance Approval (CLI-ECA) is a streamlined approval process for municipalities managing wastewater, stormwater, and Low Impact Development (LID) infrastructure. The CLI-ECA replaces the need for municipalities to apply for multiple, project-specific Environmental Compliance Approvals (ECAs) every time they want to make changes or additions to their water, wastewater, or stormwater collection systems. CLI-ECAs authorize municipalities to make changes to the system when requirements in the CLI-ECA are met (MECP, 2024)[2]. MECP requires all municipalities in Ontario to enroll into the CLI-ECA program by application. Each municipality will receive:
- One CLI-ECA for their municipal sewage collection system
- One CLI-ECA for their municipal stormwater management system (MECP, 2025)[3]
Step-by-step compliance process[edit]
Step 1: Determine if your project falls under CLI-ECA[edit]
If you are a developer or prescribed person, contact the municipality where your project is located to determine if they have received a CLI-ECA and obtain a copy. You must then identify whether the proposed wastewater or stormwater project qualifies as a pre-authorized alteration under the CLI-ECA. Common eligible projects include:
Stormwater:
- Storm sewer upgrades or extensions
- Alterations to stormwater management facilities (e.g., wet ponds, dry ponds, wetlands)
- Implementation or modification of LID practices (e.g., bioretention, infiltration trenches, permeable pavements)
Wastewater:
- Sewage works used for the collection, storage, pumping, and transmission of sanitary sewage, excluding treatment
- Municipal-owned eligible sewage works for collection of sanitary sewage
- Combined sewers and combined sewage storage structures that collect and convey both wastewater from residential, commercial, institutional and industrial buildings and stormwater runoff through a single-pipe system
- Pumping stations
- Sewage works used for the management of residue or odour
If you determine that your project falls under the CLI-ECA, refer to the municipality for guidance on how to submit an application. Works that do not qualify as a pre-authorized alteration under the CLI-ECA must instead go through a standalone, project-specific Environmental Compliance Approval (ECA) process
Step 2: Review design criteria and standards[edit]
Ensure project design and objectives follow:
- MECP’s Design Criteria for Sanitary Sewers, Storm Sewers and Forcemains for Alterations Authorized under an Environmental Compliance Approval (2023)
- Design Guidelines For Sewage Works
- Low Impact Development Stormwater Management Guidance Manual Draft (MECP, 2022)[4].
- Ontario Stormwater Management Planning and Design Guidance Manual (MOE, 2003)Cite error: Closing
</ref>missing for<ref>tag. Below is MECP's Guide to Applying for the First Consolidated Linear Infrastructure Environmental Compliance Approval (2021)[5] and an example Environmental Compliance Approval for the City of Peterborough's stormwater system (2023)[6]. You can download (downward facing arrow on the top righthand side) and print (Printer emoticon on top right hand side) each PDF.
Annual reports[edit]
Municipalities in Ontario are required to submit annual performance reports as per the conditions in the CLI-ECA, which must be made available to the public at no charge. Specific requirements for the report will be listed in the CLI-ECA, but typically include (MECP, 2024)[2]:
- the timeframe that the report must cover and due date
- monitoring data and environmental trends
- operating problems encountered and corrective action
- maintenance and repair activities undertaken
- complaints received about the system and steps taken to address them
- spills and abnormal discharge events
- changes made to the system and any actions to improve or correct performance of the system
Below are examples of these reports, including Mississauga's Stormwater System Performance Report (2024)[7], Newmarket's Wastewater System Performance Report (2024)[8], and Wellington's Stormwater System Performance Report (2024)[9]. You can download (downward facing arrow on the top righthand side) and print (Printer emoticon on top right hand side) each PDF.
Operations and maintenance manuals[edit]
Conditions in the CLI ECA require the municipality to prepare and implement an operations and maintenance manual for the system. Requirements for what must be included in an O&M manual are listed in the CLI-ECA, but will typically include (MECP, 2024) [2]:
- operating and maintenance procedures for routine operation of the system
- inspection programs, including frequency of inspection and the methods or tests used to detect when maintenance is necessary
- maintenance and repair programs
- operational and maintenance requirements to protect sources of drinking water, such as those included in the ministry’s Standard Operating Policies for Sewage Works Document. This procedure can be *downloaded through Environmental Registry #012-2968 and any applicable local source protection plan policies
- procedures for the inspection and calibration of monitoring equipment
- emergency response, spill reporting, contingency plans and procedures for dealing with equipment breakdowns, potential spills and any other abnormal situations
- procedures for receiving, responding and recording public complaints
- as-built drawings or record drawings
Click on the image to read a presentation on O&M Manual Development under the CLI-ECA by the Town of Newmarket (2025)[10].
Monitoring[edit]
This section will be updated as information becomes available.
Updates[edit]
2020
- CLI-ECA introduced (Environmental Registry of Ontario, 2020)[11]
2023
- Monitoring guidance draft under review with existing technical stakeholder working group – need for revisions identified
Click on the button below to read the 2023 Source to Stream Conference Presentation by MECP and LSRCA[1]
2025
- Monitoring Guidance for CLI-ECA is under internal review. Note: municipalities are allowed up to two years from the date of publication of the guidance document to develop and implement a monitoring plan that meets the ECA requirements
Click on the button below to read the 2025 Source to Stream Conference Presentation by MECP[3]
References[edit]
- ↑ 1.0 1.1 MECP and LSRCA. 2023. Panel Presentation: Monitoring and the Consolidated Linear Infrastructure Environmental Compliance Approval (CLI-ECA) Framework: Understanding and Applying Ontario’s New Requirements for Municipal Stormwater Infrastructure. Source to Stream Conference. https://sourcetostream.com/2023-panel/
- ↑ 2.0 2.1 2.2 2.3 MECP. 2024. https://www.ontario.ca/page/municipal-consolidated-linear-infrastructure-environmental-compliance-approvals
- ↑ 3.0 3.1 MECP. 2025. Bringing the CLI-ECA Framework into Action: Guiding Principles to Inform Stormwater Management Practices. Source to Stream Conference Presentation. https://sourcetostream.com/app/uploads/2025/04/Day-2-Hall-A-Presentation-2-DSmith-AAhmed.pdf
- ↑ MECP. 2022. Low Impact Development Stormwater Management Guidance Manual Draft. https://ero.ontario.ca/public/2022-01/Draft%20LID%20Stormwater%20Management%20Guidance%20Manual%202022.pdf
- ↑ MECP. 2021. Guide to Applying for the First Consolidated Linear Infrastructure Environmental Compliance Approval. https://wcwc.ca/wp-content/uploads/2024/05/CLI-ECA-Application-Guide.pdf
- ↑ Environmental Compliance Approval For a Municipal Stormwater Management System. https://www.peterborough.ca/media/ucbdw0wf/eca-number-145-s701-storm-issue-2.pdf
- ↑ City of Mississauga. 2024. 2024 Annual Performance Report – Mississauga Stormwater Management System. https://www.mississauga.ca/wp-content/uploads/2025/05/12153249/2024-Annual-Performance-Report-Mississauga-stormwater-system.pdf
- ↑ Town of Newmarket. 2024. Annual Wastewater Collection System Performance Report. https://care.newmarket.ca/LivingHere/Documents/Wastewater%20Reports/TON%202024%20Annual%20Wastewater%20Collection%20System%20Performance%20Report.pdf
- ↑ Wellington County. 2024. Wellington County Stormwater Management System Annual Performance Report. https://www.wellington.ca/media/file/2024-annual-performance-reportpdf
- ↑ Schritt, C. & MacDonald, M. 2025. Stormwater Under Pressure: Navigating O&M Manual Development under the CLI-ECA. Source to Stream Conference Presentation. https://sourcetostream.com/2025-track-1-day-2-schritt-macdonald/
- ↑ Environmental Registry of Ontario. 2020. Proposed changes to environmental approvals for municipal sewage collection works. https://ero.ontario.ca/notice/019-1080#:~:text=We%20anticipate%20receiving%20the%20first,ready%20to%20transition%20to%20CLI%20.