===Small-scale projects===
 +
Starting with small-scale projects is a good strategy to
 +
increase public interest in LID practices, gauge municipal
 +
support, and gain retrofit experience. Small-scale projects
 +
include retrofitting your site with landscape alternatives or rain
 +
barrels, enhancements of existing swales, or using pollution
 +
prevention strategies and practices.
 +
 +
Small-scale projects require fewer resources and require a
 +
smaller project budget because:
 +
* They do not require integration into capital works
 +
projects
 +
* Engineering consultants are not required
 +
* Contractors may not be required
 +
* External approvals are not required
 +
* Consultation with the public is limited
 +
 +
Due to this smaller financial commitment, it can be easier
 +
to build colleague and supervisor support for small-scale
 +
projects.
 +
 +
[[Pollution prevention|Pollution prevention (P2)]] projects are great
 +
small-scale projects for municipal facilities
 +
like public works yards. To learn more about
 +
implementing P2 on your site, '''refer to the case studies on Armstrong Manufacturing Inc, Bernardi Building Supply Ltd. and Unifay-Fedar Investments in Appendix B.'''
 +
 +
Many P2 techniques and strategies do not require
 +
construction, consultants or contractors. Adding signage to a
 +
site is a simple and easy to implement pollution prevention at
 +
municipal facilities.
 +
 +
A successful small-scale LID retrofit project on your municipal
 +
site is a good indication that you are ready to take on a more
 +
intensive retrofit project. You now know the resources that are
 +
available and understand the internal municipal processes
 +
required to move a LID project from planning to finished
 +
product.
 +
 +
===Large-scale projects===
 +
 +
Large-scale projects require significantly more effort, budget,
 +
and staff than small-scale projects. Large-scale LID retrofits
 +
include:
 +
* Bioretention
 +
* Enhanced grass swales
 +
* Bioswales
 +
* Perforated pipe systems
 +
* Permeable pavement
 +
* Soakaways
 +
* Infiltration chambers
 +
* Rainwater harvesting (excluding rain barrels)
 +
* Prefabricated modules
 +
* Green roofs
 +
 +
Consider a large-scale project if your municipality or
 +
department would like to be a leader in sustainability. Large-scale
 +
projects are often highly visible and attract more public
 +
attention. Large-scale projects may also be the only solution
 +
to site-specific challenges. For example, if site infrastructure
 +
is at risk as a result of urban flooding, LID practices that detain
 +
large volumes of runoff and encourage infiltration are the
 +
most viable LID options.
 +
Before starting a large-scale retrofit project, consider the
 +
following distinctions that set these retrofits apart from small-scale
 +
projects.
 +
 +
===Integration with capital works programs===
 +
 +
Most large-scale LID retrofits must function with existing
 +
site infrastructure, such as storm sewers, catch basins,
 +
and pavement systems. The construction of large-scale
 +
LID practices often requires these systems to be removed,
 +
exposed, or replaced. The best time for this type of project to
 +
occur is when an infrastructure replacement or rehabilitation
 +
project is already planned.
 +
 +
When LID retrofits are worked into other construction
 +
projects, such as parking lot repaving, or grading or drainage
 +
improvements, there can be substantial cost savings.
 +
Whether big or small, every municipality spends relatively
 +
large sums of money and substantial time planning for
 +
major capital projects. This includes redevelopment of public
 +
building and spaces. Many communities who have undertaken
 +
retrofits recognize that even if a relatively small portion of the
 +
project funds goes towards LID retrofits, they can retrofit large
 +
impervious surfaces and avoid new stormwater management
 +
infrastructure projects17.
 +
 +
Municipal facility rehabilitation is typically forecast well in
 +
advance of the project. Parking lot paving is typically worked
 +
into municipal budgets based on expected life cycle and
 +
observed wear. As such, funds may be set aside prior to
 +
the project planning phases. Long-term forecast budgets
 +
may also be available for site revitalizations or expansions.
 +
These budget forecasts provide opportunities to compare the
 +
capital and life-cycle costs and benefits of the conventional
 +
construction project and LID retrofit.
 +
 +
===Involvement of consultants and contractors===
 +
Consultants are required for large-scale retrofit projects,
 +
specifically for the final screening of options, pre-design,
 +
detailed design, tender and contract documents, construction
 +
supervision and administration, and assumption and
 +
verification.
 +
 +
Site contractors are also required for large-scale LID retrofits.
 +
Ideally, contractors should be pre-qualified based on previous
 +
experience with similar LID projects.
 +
Remember, the contractor with the lowest bid
 +
does not necessarily deliver the best product.
 +
 +
===More intensive public consultation===
 +
 +
Stakeholders must be closely involved in the retrofit process
 +
for large-scale LID projects. These projects have longer
 +
construction windows, may have significant impacts on long-term
 +
public use patterns of the site, and will cost significantly
 +
more taxpayer dollars.
 +
 +
Gaining public insight in advance of LID implementation can
 +
help address public concerns and information gaps, as well as identify public supporters and champions. Public consultation
 +
can help designers tailor the project to address community
 +
concerns and values. Consultation can also help the design
 +
team integrate the LID practice into the site’s landscape.
 +
 +
===External approvals===
 +
 +
Large-scale retrofits may require a variety of approvals at the
 +
municipal, watershed, provincial, and/or federal level.
 +
Since LID is still relatively new, you may encounter policies
 +
or bylaws that present barriers to LID retrofit projects.
 +
Alternatively, the municipality may have to amend or enforce
 +
some policies and bylaws to facilitate the implementation of
 +
LID projects on your site.
    