The Municipal Consolidated Linear Infrastructure Environmental Compliance Approval (CLI-ECA) is a streamlined approval process for municipalities managing stormwater and Low Impact Development (LID) infrastructure. This guide offers step-by-step instructions to ensure compliance with CLI-ECA requirements.
 
The Municipal Consolidated Linear Infrastructure Environmental Compliance Approval (CLI-ECA) is a streamlined approval process for municipalities managing stormwater and Low Impact Development (LID) infrastructure. This guide offers step-by-step instructions to ensure compliance with CLI-ECA requirements.
Line 16: Line 16:
 
===Step 3: Complete Required Documentation===
 
===Step 3: Complete Required Documentation===
 
Use the appropriate compliance forms based on project type:
 
Use the appropriate compliance forms based on project type:
*[[Media:Form_SW1_-_STM_-_May25-2022.pdf|Form SW1 – Storm Sewers/Ditches/Culverts​]]
+
 
*[[Media:Form_SW2_-_STM_-_May25-2022.pdf|Form SW2 – Stormwater Management Facilities]]
+
{{clickable button|[[Media:Form_SW1_-_STM_-_May25-2022.pdf|Form SW1 – Storm Sewers/Ditches/Culverts​]]}}
*[[Media:Form SW3 - STM - May25-2022.pdf|Form SW3 – Third Pipe Collection Systems]]  
+
{{clickable button|[[Media:Form_SW2_-_STM_-_May25-2022.pdf|Form SW2 – Stormwater Management Facilities]]}}
 +
{{clickable button|[[Media:Form SW3 - STM - May25-2022.pdf|Form SW3 – Third Pipe Collection Systems]]}}
  
 
Prepare a Design Report including:
 
Prepare a Design Report including:
Line 52: Line 53:
 
* Routine inspections (e.g., [[sediment]] removal, [[vegetation]] management)
 
* Routine inspections (e.g., [[sediment]] removal, [[vegetation]] management)
 
* Adaptive management strategies for system improvements
 
* Adaptive management strategies for system improvements
Retain compliance records for a minimum of **10 years**.
+
Retain compliance records for a minimum of 10 years.
 
Submit annual performance reports if required by municipal or provincial regulations.
 
Submit annual performance reports if required by municipal or provincial regulations.
  

Latest revision as of 15:54, 3 February 2025

TrilliumMECP.jpeg

The Municipal Consolidated Linear Infrastructure Environmental Compliance Approval (CLI-ECA) is a streamlined approval process for municipalities managing stormwater and Low Impact Development (LID) infrastructure. This guide offers step-by-step instructions to ensure compliance with CLI-ECA requirements.

Step-by-Step Compliance Process[edit]

Step 1: Determine if Your Project Falls Under CLI-ECA[edit]

Identify whether the proposed stormwater or LID project qualifies as a pre-authorized alteration under CLI-ECA. Common eligible projects include:

Step 2: Review Design Criteria and Standards[edit]

Step 3: Complete Required Documentation[edit]

Use the appropriate compliance forms based on project type:

Form SW1 – Storm Sewers/Ditches/Culverts​ Form SW2 – Stormwater Management Facilities Form SW3 – Third Pipe Collection Systems

Prepare a Design Report including:

Step 4: Obtain Engineering and Owner Verification[edit]

A Licensed Engineering Practitioner must verify that:

  • The design aligns with CLI-ECA criteria.
  • The system is designed for proper stormwater management without negative impacts.

The Municipal Owner must sign off on compliance forms confirming:

  • The alteration does not result in adverse effects.
  • It aligns with jurisdictional stormwater management objectives.

Step 5: Submit a Director Notification (If Required)[edit]

Some alterations require notification to the MECP Director within specific timeframes:

  • 30 days after placing new works into service.
  • 90 days if previously undocumented infrastructure is discovered.

The notification must include:

  • Project description
  • Verification documents
  • Compliance assessment

Step 6: Conduct Post-Construction Inspection and Verification[edit]

  • Inspect LID and stormwater systems to ensure they function as designed.
  • Complete "Post-Construction Verification" on relevant forms.
  • Document key performance indicators such as infiltration rates, flow control effectiveness, and pollutant removal efficiency.

Step 7: Maintain Ongoing Compliance and Record-Keeping[edit]

Establish a Stormwater System Maintenance Plan that includes:

  • Routine inspections (e.g., sediment removal, vegetation management)
  • Adaptive management strategies for system improvements

Retain compliance records for a minimum of 10 years. Submit annual performance reports if required by municipal or provincial regulations.