Pipes should have been manufactured in conformity with the latest standards by the Canadian Standards Association (CSA) or ASTM International.
 
Pipes should have been manufactured in conformity with the latest standards by the Canadian Standards Association (CSA) or ASTM International.
 
*Perforated pipes should be continuously perforated, smooth interior HDPE (or equivalent material).
 
*Perforated pipes should be continuously perforated, smooth interior HDPE (or equivalent material).
**Wherever possible pipes should be ≥ 200 mm internal diameter to reduce clogging and to facilitate inspections and maintenance.  
+
**Wherever possible pipes should be ≥ 200 mm internal diameter to reduce potential of freezing and to facilitate inspections and maintenance with a push camera.  
 
**Smooth interior facilitates inspection and maintenance activities; internal corrugations can cause cameras or hydrojetting apparatus to become snagged.     
 
**Smooth interior facilitates inspection and maintenance activities; internal corrugations can cause cameras or hydrojetting apparatus to become snagged.     
 
**A perforated pipe with many rectangular slots has better drainage characteristics than a pipe with similar open area provided by fewer circular holes <ref>Hazenberg, G., and U. S. Panu (1991), Theoretical analysis of flow rate into perforated drain tubes, Water Resour. Res., 27(7), 1411–1418, doi:10.1029/91WR00779.</ref>.
 
**A perforated pipe with many rectangular slots has better drainage characteristics than a pipe with similar open area provided by fewer circular holes <ref>Hazenberg, G., and U. S. Panu (1991), Theoretical analysis of flow rate into perforated drain tubes, Water Resour. Res., 27(7), 1411–1418, doi:10.1029/91WR00779.</ref>.
*Non-perforated pipes should be used for conveyance to and away from the facility, including [[overflow]]. It is good practice to extend the non-perforated pipe approximately 300 mm within the reservoir or practice to reduce the chance of migration from native soils clogging the pipe at the interface.  
+
*Non-perforated pipes should be used for conveyance to and away from the facility, including [[overflow]]. It is good practice to extend the non-perforated pipe approximately 300 mm within the reservoir or practice to reduce the potential for native soil migration to clog the pipe at the interface.  
  
 
<gallery mode="packed" widths=200px heights=200px>
 
<gallery mode="packed" widths=200px heights=200px>

Revision as of 22:11, 21 April 2020

Pipes are available with perforations on just one side, these should be situated on the lower half of the pipe. Pipes with 360° perforations should have a strip of geotextile or membrane placed over the pipe to reduce the migration of fines from overlying media.

Perforated pipes are a common component of underdrains, infiltration trenches and exfiltration trenches.

Pipes should have been manufactured in conformity with the latest standards by the Canadian Standards Association (CSA) or ASTM International.

  • Perforated pipes should be continuously perforated, smooth interior HDPE (or equivalent material).
    • Wherever possible pipes should be ≥ 200 mm internal diameter to reduce potential of freezing and to facilitate inspections and maintenance with a push camera.
    • Smooth interior facilitates inspection and maintenance activities; internal corrugations can cause cameras or hydrojetting apparatus to become snagged.
    • A perforated pipe with many rectangular slots has better drainage characteristics than a pipe with similar open area provided by fewer circular holes [1].
  • Non-perforated pipes should be used for conveyance to and away from the facility, including overflow. It is good practice to extend the non-perforated pipe approximately 300 mm within the reservoir or practice to reduce the potential for native soil migration to clog the pipe at the interface.

See also: flow through perforated pipe


  1. Hazenberg, G., and U. S. Panu (1991), Theoretical analysis of flow rate into perforated drain tubes, Water Resour. Res., 27(7), 1411–1418, doi:10.1029/91WR00779.