Overview

Permeable pavingAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. allows stormwater to drain through the surface and into a stone reservoirAn underlying bed filled with aggregate or other void-forming fill material that temporarily stores stormwater before infiltrating into the native soil or being conveyed by an underdrain pipe., where it infiltrates into the underlying native soilThe natural ground material characteristic of or existing by virtue of geographic origin. or is temporarily detained.

The following are different types of permeable pavingAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil.:
  • Permeable interlocking concrete pavers
  • Plastic or concrete grid systems
  • Pervious concrete
  • Pervious asphaltA mixture of mineral aggregates bound with bituminous materials, used in the construction and maintenance of paved surfaces.

Permeable pavingAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. is ideal for:

  • Sites with limited space for other surface stormwater BMPs
  • Projects such as low traffic roads, parking lots, driveways, pedestrian plazas and walkways

The fundamental components of a permeable pavingAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. system are:

  • interlocking blocks with infiltration spaces between
  • Precast pervious slabs or pavers
  • a cast in place surface without finesSoil particles with a diameter less than 0.050 mm., so that the finish is pervious to water
  • a bedding course to stabilize the surface
  • underground storage layer of aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations.

Additional components may include:

  • an underdrainA perforated pipe used to assist the draining of soils. system

Planning considerations

Geometry and Site Layout

Permeable pavingAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. can be used for entire parking lot areas or driveways and can be designed to receive runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. from adjacent imperviousA hard surface area (e.g., road, parking area or rooftop) that prevents or retards the infiltration of water into the soil. surfaces. For example, the parking spaces in a parking lot may be permeable pavers while the drive lanes themsevles are imperviousA hard surface area (e.g., road, parking area or rooftop) that prevents or retards the infiltration of water into the soil. asphaltA mixture of mineral aggregates bound with bituminous materials, used in the construction and maintenance of paved surfaces..

In general, the imperviousA hard surface area (e.g., road, parking area or rooftop) that prevents or retards the infiltration of water into the soil. area should not exceed 1.2 times the area of the permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. which receives the runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface.. A hybrid permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil./soakawayAn underground water storage reservoir into which stormwater is directed and allowed to percolate into the underlying native subsoil.An excavated area lined with geotextile filter cloth and filled with clean granular stone or other void forming material, that receives runoff and allow it to infiltrate into the native soil; can also be referred to as infiltration galleries, French drains, dry wells or soakaway pits. design can feature connection of a roof downspout directly to the stone reservoirAn underlying bed filled with aggregate or other void-forming fill material that temporarily stores stormwater before infiltrating into the native soil or being conveyed by an underdrain pipe. of the permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. system, which is sized to store runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. from both the pavement surface and the roof drainage areaThe total surface area upstream of a point on a stream that drains toward that point. Not to be confused with watershed. The drainage area may include one or more watersheds..

PretreatmentInitial capturing and removal of unwanted contaminants, such as debris, sediment, leaves and pollutants, from stormwater before reaching a best management practice; Examples include, settling forebays, vegetated filter strips and gravel diaphragms.

In most designs, the surface acts as pretreatmentInitial capturing and removal of unwanted contaminants, such as debris, sediment, leaves and pollutants, from stormwater before reaching a best management practice; Examples include, settling forebays, vegetated filter strips and gravel diaphragms. to the stone reservoirAn underlying bed filled with aggregate or other void-forming fill material that temporarily stores stormwater before infiltrating into the native soil or being conveyed by an underdrain pipe. below. Periodic vacuum sweeping and preventative measures like not storing snow or other materials on the pavement are critical to prevent clogging. Another pretreatmentInitial capturing and removal of unwanted contaminants, such as debris, sediment, leaves and pollutants, from stormwater before reaching a best management practice; Examples include, settling forebays, vegetated filter strips and gravel diaphragms. element is a pea gravel choking layer above the coarse gravel storage reservoirAn underlying bed filled with aggregate or other void-forming fill material that temporarily stores stormwater before infiltrating into the native soil or being conveyed by an underdrain pipe..

Landscaping

Landscaped areas must drain away from permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. to prevent sedimentsSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. from running onto the surface. Urban trees will benefit from being surrounded by permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. rather than imperviousA hard surface area (e.g., road, parking area or rooftop) that prevents or retards the infiltration of water into the soil. cover, because their roots receive more air and water. Interlocking pavers used around the base of a tree may be removed as the tree grows.

Risk of Groundwater Contamination

  • Stormwater infiltration practices should not receive runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. from high traffic areas where large amounts of de-icing salts are applied (e.g., busy highways), nor from pollution hot spots (e.g., source areas where land uses or activities have the potential to generate highly contaminated runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. such as vehicle fuelling, servicing or demolition areas, outdoor storage or handling areas for hazardous materials and some heavy industry sites)
  • Prioritize infiltration of runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. from source areas that are comparatively less contaminated such as roofs, low traffic roads and parking areas
  • Apply sedimentationDeposition of material of varying size, both mineral and organic away from its site of origin by the action of water, wind, gravity or ice.Settling-out or deposition of particulate matter suspended in runoff. pretreatmentInitial capturing and removal of unwanted contaminants, such as debris, sediment, leaves and pollutants, from stormwater before reaching a best management practice; Examples include, settling forebays, vegetated filter strips and gravel diaphragms. practices (e.g., oil and grit separators) before infiltration of road or parking area runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface.

Heavy Vehicle Traffic

Permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. is not typically used in locations subject to heavy loads. However, some permeable pavers are designed for heavy loads and have been used in commercial port loadingThe total mass of a pollutant entering a waterbody over a defined time period.The net amount of something (e.g. chemical, such as phosphorus), calculated as the product of concentration and volume in a given time. Some BMPs significantly reduce loading of pollutants to the environment by reducing volume more so than concentration. and storage areas.

Setbacks from Buildings

Permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. should be located downslope from building foundations. If the pavement does not receive runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. from other surfaces, no setback is required from building foundations. Otherwise, a minimum setback of 4 m down-gradient from building foundations is recommended.

On Private PropertyLand owned by private individuals or companies.

If permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. systems are installed on private lots, property owners or managers will need education on their routine maintenance needs, understanding the long-term maintenance plan. They may also be subject to a legally binding maintenance agreement. An incentive program, such as a storm sewer user fee based on the area of imperviousA hard surface area (e.g., road, parking area or rooftop) that prevents or retards the infiltration of water into the soil. cover on a property that is directly connected to a storm sewer, could be used to encourage property owners or managers to maintain existing practices.

Design

Modeling permeable pavingAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. in the Treatment Train Tool

Permeable paving: TTT

Sizing Stone Reservoirs

Permeable paving: Sizing and modeling

Materials

Consult the manufacturer for the design specifications of their product. In pervious concrete and porous asphaltA mixture of mineral aggregates bound with bituminous materials, used in the construction and maintenance of paved surfaces. systems, the concrete or asphaltA mixture of mineral aggregates bound with bituminous materials, used in the construction and maintenance of paved surfaces. mix specifications and construction procedures are key to proper functioning. These systems require well-trained and experienced contractors for installation.
Specifications

Stone Reservoir

The stone reservoirAn underlying bed filled with aggregate or other void-forming fill material that temporarily stores stormwater before infiltrating into the native soil or being conveyed by an underdrain pipe. must meet both runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. storage and structural support requirements. The bottom of the reservoir should be level so that water infiltrates evenly. If the system is not designed for infiltrationThe slow movement of water into or through a soil or drainage system.Penetration of water through the ground surface., the bottom should slope at 1 - 5% toward the underdrainA perforated pipe used to assist the draining of soils.. This is a collection of three articles with the common theme of being aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. products for various applications in LIDLow Impact Development. A stormwater management strategy that seeks to mitigate the impacts of increased urban runoff and stormwater pollution by managing it as close to its source as possible. It comprises a set of site design approaches and small scale stormwater management practices that promote the use of natural systems for infiltration and evapotranspiration, and rainwater harvesting..

Underground construction aggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations.

For reservoirs

Note the uniform size and angularity of this clear stone sample. Note also that the fragments all appear to have a film of fine particles adhering; this material would be improved by being washed prior to use.

This article gives recommendations for aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. to be used to store water for infiltrationThe slow movement of water into or through a soil or drainage system.Penetration of water through the ground surface.. This is usually called 'clear stone' at aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. yards.

To see an analysis of Ontario Standard Specifications for granularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices. materials, see OPSS aggregates.

For advice on decorative surface aggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. see Stone


Gravel used for underdrains in bioretention, infiltration trenches and chambers, and exfiltration trenches should be 20 or 50 mm, uniformly-graded, clean (maximum wash loss of 0.5%), crushed angular stone that has a porosityThe porosity (n) of a mixture is the ratio of the volume of void-space to the total or bulk volume of the mixture. It is closely related to the concept of void ratio (e) where void ratio is the ratio of the volume of void-space to the volume of solids. n = Volume of voids/Total volume of mixture = e/(1+e) of 0.4[1].

The clean wash to prevent rapid accumulation of finesSoil particles with a diameter less than 0.050 mm. from the aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. particles in the base of the reservoir. The uniform grading and the angularity are important to maintain pore throats and clear voids between particles. (i.e. achieve the porosityThe porosity (n) of a mixture is the ratio of the volume of void-space to the total or bulk volume of the mixture. It is closely related to the concept of void ratio (e) where void ratio is the ratio of the volume of void-space to the volume of solids. n = Volume of voids/Total volume of mixture = e/(1+e)). PorosityThe porosity (n) of a mixture is the ratio of the volume of void-space to the total or bulk volume of the mixture. It is closely related to the concept of void ratio (e) where void ratio is the ratio of the volume of void-space to the volume of solids. n = Volume of voids/Total volume of mixture = e/(1+e) and permeability are directly influenced by the size, gradation and angularity of the particles [2]. See jar test for on-site verification testing protocols.

Gravel with structural requirements should also meet the following criteria:

  • Minimum durability index of 35
  • Maximum abrasion of 10% for 100 revolutions and maximum of 50% for 500 revolutions

Standard specifications for the gradation of aggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. are maintained by ASTM D2940


For choking/choker layers

medium sized granularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices., free from finesSoil particles with a diameter less than 0.050 mm.

In bioretention systems a choker layer of ≥ 100 mm depth is the recommended method to prevent migration of finer filter media into the underlying storage reservoir aggregate. These same mid-sized granularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices. materials are recommended for use in Stormwater planter underdrains and may be useful in the fine grading of foundations courses for permeable pavements.

Suitable materials include:

High performance bedding (HPB)
Clean, angular aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. screened to between 6 and 10 mm. Widely available and designed specifically for drainage applications. Free from finesSoil particles with a diameter less than 0.050 mm. by definition.
HL 6
Is a clean, angular aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. screened between 10 and 20 mm. Free from finesSoil particles with a diameter less than 0.050 mm. by definition.
Pea Gravel
Rounded natural aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations., screened between 5 and 15 mm, and washed free from finesSoil particles with a diameter less than 0.050 mm..

In most scenarios, a geotextile layer is unnecessary and has been associated with rapid decline and clogging in some circumstances.


OPS AggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations.

Of the standard granularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices. materials in the standard OPSS.MUNI 1010 only GranularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices. O is recommended as a substitute for clear stone in LIDLow Impact Development. A stormwater management strategy that seeks to mitigate the impacts of increased urban runoff and stormwater pollution by managing it as close to its source as possible. It comprises a set of site design approaches and small scale stormwater management practices that promote the use of natural systems for infiltration and evapotranspiration, and rainwater harvesting. construction.

Where GranularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices. O is substituted for clear stone in underground reservoir structures, the porosityThe porosity (n) of a mixture is the ratio of the volume of void-space to the total or bulk volume of the mixture. It is closely related to the concept of void ratio (e) where void ratio is the ratio of the volume of void-space to the volume of solids. n = Volume of voids/Total volume of mixture = e/(1+e) used in design calculations shall be 0.3 unless laboratory testing proves otherwise.

Examples of BMPs with underground reservoirs include Underdrains, infiltration trenches, permeable pavements, infiltration chambers, exfiltration trenches.

All other mixes must be avoided for free drainage or storage as they are permitted to contain a higher enough proportion of finesSoil particles with a diameter less than 0.050 mm. to reduce permeability below 50 mm/hr.

For more information see OPS aggregates

Landscaping aggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations.

This rain gardenA lot level bioretention cell designed to receive and detain, infiltrate and filter runoff, typically used for discharge from downspouts. in a school yard uses stone as both decorative edging and for erosion controlIncludes the protection of soil from dislocation by water, wind or other agents..
This bioswaleLinear bioretention cell designed to convey, treat and attenuate stormwater runoff. The engineered filter media soil mixture and vegetation slows the runoff water to allow sedimentation, filtration through the root zone, evapotranspiration, and infiltration into the underlying native soil. in a parking lot uses stone at the inlets and along the bottom of the swaleA shallow constructed channel, often grass-lined, which is used as an alternative to curb and channel, or as a pretreatment to other measures. Swales are generally characterized by a broad top width to depth ratio and gentle grades. to prevent erosion(1) The wearing away of the land surface by moving water, wind, ice or other geological agents, including such processes as gravitation creep; (2) Detachment and movement of soil or rock fragments by water, wind, ice or gravity (i.e. Accelerated, geological, gully, natural, rill, sheet, splash, or impact, etc)., as the sides are sloped.

For advice on aggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. used in underdrains, see Reservoir aggregate.

Stone or gravel can serve as a low maintenance decorative feature, but it may also serve many practical functions on the surface of an LIDLow Impact Development. A stormwater management strategy that seeks to mitigate the impacts of increased urban runoff and stormwater pollution by managing it as close to its source as possible. It comprises a set of site design approaches and small scale stormwater management practices that promote the use of natural systems for infiltration and evapotranspiration, and rainwater harvesting. practice.

Stone for erosion controlIncludes the protection of soil from dislocation by water, wind or other agents.

AggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. used to line swales or otherwise dissipate energy (e.g. in forebays) should have high angularity to increase the permissible shear stress applied by the flow of water. [3] However, in some surface landscaped applications there may be a desire to use a rounded aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. such as 'river rock' for aesthetic reasons. Rounded stones should be of sufficient size to resist being moved by the flow of water. Typical stone for this purpose ranges between 50 mm and 250 mm in diameter. The larger the stone, the more energy dissipation.

  • Stone beds should be twice as thick as the largest stone's diameter.
  • If the stone bed is underlain by a drainage geotextile, annual inspection and possible replacement should be performed as there is a potential for clogging of this layer to occur.

Stone mulcha top dressing over vegetation beds that provides suppresses weeds and helps retain soil moisture in bioretention cells, stormwater planters and dry swales.

Finer inorganic mulcha top dressing over vegetation beds that provides suppresses weeds and helps retain soil moisture in bioretention cells, stormwater planters and dry swales. materials can be of value applied in areas with extended ponding times i.e. in the the centre of recessed, bowl shaped bioretention, stormwater planters, trenches or swale practices. Inorganic mulches resist movement from flowing water and do not float. Applying a thin layer of inorganic mulcha top dressing over vegetation beds that provides suppresses weeds and helps retain soil moisture in bioretention cells, stormwater planters and dry swales. over the top of wood based mulcha top dressing over vegetation beds that provides suppresses weeds and helps retain soil moisture in bioretention cells, stormwater planters and dry swales. has been shown to reduce migration of the underlying layer by around 25% [4]. Inorganic mulches which may be available locally, include:

  • Pea gravel
  • River rock/beach stone
  • Recycled glass
  • Crushed mussel shells

On-site verification

Steps in conducting a jar test to detect finesSoil particles with a diameter less than 0.050 mm. in construction materials

Specifying that aggregates for the construction of LIDLow Impact Development. A stormwater management strategy that seeks to mitigate the impacts of increased urban runoff and stormwater pollution by managing it as close to its source as possible. It comprises a set of site design approaches and small scale stormwater management practices that promote the use of natural systems for infiltration and evapotranspiration, and rainwater harvesting. practices must be free from finesSoil particles with a diameter less than 0.050 mm. is important. But checking that the delivered materials meet specification is essential to reduce problems with construction and longer term performance.

When possible, Construction Managers should observe the offloading of materials to watch for dust clouds. AggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. or sand for LIDLow Impact Development. A stormwater management strategy that seeks to mitigate the impacts of increased urban runoff and stormwater pollution by managing it as close to its source as possible. It comprises a set of site design approaches and small scale stormwater management practices that promote the use of natural systems for infiltration and evapotranspiration, and rainwater harvesting. construction should not give rise to clouds of dust when dumped.

A simple jar test can be used to gauge the proportion of finesSoil particles with a diameter less than 0.050 mm. in an aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. product before acceptance.

Apparatus:

  • A large wide-mouthed jar - glass or clear plastic are both fine,
  • Tap water, and
  • The aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. to be tested.

Method:

  1. Collect approximately 5 cm of material in the jar (or at least two complete layers of 50 mm clear stone),
  2. Add water to around 3/4 full,
  3. Secure cap and shake,
  4. Leave for at least 30 minutes and until the water is clear - plan to run the test overnight when possible,
  5. Examine the layer of sedimentSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. - if > 3 mm has been washed from 5 cm of product, the material should be rejected,

Note that the sedimentSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. may collect on top of, or at the bottom of the construction material.

External references

GeotextileFilter fabric that is installed to separate dissimilar soils and provide runoff filtration and contaminant removal benefits while maintaining a suitable rate of flow; may be used to prevent fine-textured soil from entering a coarse granular bed, or to prevent coarse granular from being compressed into underlying finer-textured soils.

The properties of geotextiles vary widely.

See Clogging for notes on their application in LIDLow Impact Development. A stormwater management strategy that seeks to mitigate the impacts of increased urban runoff and stormwater pollution by managing it as close to its source as possible. It comprises a set of site design approaches and small scale stormwater management practices that promote the use of natural systems for infiltration and evapotranspiration, and rainwater harvesting. structures.

Geotextiles can be used to prevent downward migration of smaller particles in to larger aggregatesA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations., and slump of heavier particles into finer underlying courses. Geotextiles are commonly used on low strength soils (CBR<4). The formation of biofilm on geotextiles has also been shown to improve water quality:

  • By degrading petroleum hydrocarbons[5]
  • By reducing organic pollutant and nutrient concentrations [6]
  • When installing geotextiles an overlap of 150 - 300 mm should be used.

Material specifications should conform to OPSS 1860 for Class II geotextileFilter fabric that is installed to separate dissimilar soils and provide runoff filtration and contaminant removal benefits while maintaining a suitable rate of flow; may be used to prevent fine-textured soil from entering a coarse granular bed, or to prevent coarse granular from being compressed into underlying finer-textured soils. fabrics [7]. Note when expansive clays are present, a non-infiltrating design may be necessary. If used, geotextileFilter fabric that is installed to separate dissimilar soils and provide runoff filtration and contaminant removal benefits while maintaining a suitable rate of flow; may be used to prevent fine-textured soil from entering a coarse granular bed, or to prevent coarse granular from being compressed into underlying finer-textured soils. socks around perforated pipes should conform to ASTM D6707 with minimum water flow rate conforming to ASTM D4491 (12,263 L/min/m2 at 5 cm head).

  • Fabrics should be woven monofilament or non-woven needle punched.
  • Woven slit film and non-woven heat bonded fabrics should not be used, as they are prone to clogging.

In choosing a product, consider:

  1. The maximum forces that will be exerted on the fabric (i.e., what tensile, tear and puncture strength ratings are required?),
  2. The load bearing ratio of the underlying native soilThe natural ground material characteristic of or existing by virtue of geographic origin. (i.e. is the geotextileFilter fabric that is installed to separate dissimilar soils and provide runoff filtration and contaminant removal benefits while maintaining a suitable rate of flow; may be used to prevent fine-textured soil from entering a coarse granular bed, or to prevent coarse granular from being compressed into underlying finer-textured soils. needed to prevent downward migration of aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. into the native soilThe natural ground material characteristic of or existing by virtue of geographic origin.?),
  3. The texture (i.e., grain size distribution) of the overlying and underlying materials, and
  4. The suitable apparent opening size (AOS) for non-woven fabrics, or percent open area (POA) for woven fabrics, to maintain water flow even with sedimentSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. and microbial film build-up.
Recommended criteria for selection of geotextileFilter fabric that is installed to separate dissimilar soils and provide runoff filtration and contaminant removal benefits while maintaining a suitable rate of flow; may be used to prevent fine-textured soil from entering a coarse granular bed, or to prevent coarse granular from being compressed into underlying finer-textured soils. fabric
Percent soil/filter mediaThe engineered soil component of bioretention cell or dry swale designs, typically with a high rate of infiltration and designed to retain contaminants through filtration and adsorption to particles. passing 0.075 mm (#200 sieve) Non-woven fabric apparent opening size (AOS, mm) Woven fabric percent open area (POA, %) Permittivity (sec-1)
>85 ≤ 0.3 - 0.1
50 - 85 ≤ 0.3 ≥ 4 0.1
15 - 50 ≤ 0.6 ≥ 4 0.2
5 - 15 ≤ 0.6 ≥ 4 0.5
≤ 5 ≤ 0.6 ≥ 10 0.5

Performance research

http://www.mdpi.com/2073-4441/7/4/1595/htm


Landscaping

Landscaping plans should reflect the permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. application. Landscaping areas should drain away from permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. to prevent sedimentsSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. from running onto the surface. Urban trees also benefit from being surrounded by permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. rather than imperviousA hard surface area (e.g., road, parking area or rooftop) that prevents or retards the infiltration of water into the soil. cover, because their roots receive more air and water. Permeable pavers used around the base of a tree can be removed as the tree grows.

Performance

Permeable pavers can be classified into two categories according to the infiltration rateThe rate at which stormwater percolates into the subsoil measured in inches per hour. of the underlying subsoil:

  • Full InfiltrationThe slow movement of water into or through a soil or drainage system.Penetration of water through the ground surface.: Full infiltration designs are more effective, because little if any of the pollutants generated on the impermeable surfaces leave the site as surface runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface.
  • Partial InfiltrationThe slow movement of water into or through a soil or drainage system.Penetration of water through the ground surface.: Partial infiltration designs with underdrains generate more runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface.

Studies in North Carolina have shown the average curve number of permeable pavements to range from a low of 45 to a high of 89. [8]
Partial infiltration designs with underdrains generate more runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface., and as a result, are often used in studies investigating the water quality impact of permeable pavements on surface waters. These studies show load reductions above 50% for total suspended solids, most metals and hydrocarbons [9][10]
As with all stormwater infiltration practices, risk of groundwater contamination from infiltration of runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. laden with road de-icing salt constituents (typically sodium and chloride) is a significant concern. Chloride ions are extremely mobile in the soil and are readily transported by percolating water to aquifersLayer of rock or soil that holds or transmits water..

Construction Considerations

Construction of permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. is a specialized project and should involve experienced contractors. The following general recommendations apply:

  • SedimentSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. Control: The treatment area should be fully protected during construction so that no sedimentSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. reaches the permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. system and proper erosion and sedimentSoil, sand and minerals washed from land into water, usually after rain. They pile up in reservoirs, rivers and harbors, destroying fish-nesting areas and holes of water animals and cloud the water so that needed sunlight might not reach aquatic plans. Careless farming, mining and building activities will expose sediment materials, allowing them to be washed off the land after rainfalls. controls must be maintained on site.
  • Weather: Porous asphaltA mixture of mineral aggregates bound with bituminous materials, used in the construction and maintenance of paved surfaces. and pervious concrete will not properly pour and set in extremely high or low temperatures [11]. One benefit to using permeable pavers is that their installation is not weather dependent.
  • Pavement placement: Properly installed permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. requires trained and experienced producers and construction contractors.

Inspection and Maintenance

Permeable pavements require regular inspection and maintenance to ensure proper functioning. The limiting factor for permeable pavers is clogging within the aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. layers, filler, or underdrainA perforated pipe used to assist the draining of soils.. Ideally, signs should be posted on the site identifying permeable paver and porous pavement areas. This can also serve as a public awareness and education opportunity. See: Permeable paving: Maintenance

Life Cycle Costs

Initial construction costs for permeable pavements are typically higher than conventional asphaltA mixture of mineral aggregates bound with bituminous materials, used in the construction and maintenance of paved surfaces. pavement surfaces, largely due to thicker aggregateA broad category of particulate material used in construction, including sand, gravel, crushed stone, slag, recycled concrete and geosynthetic aggregates, and available in various particulate size gradations. base needed for stormwater storage. However, the cost difference is reduced or eliminated when total life-cycle costs, or the total cost to construct and maintain the pavement over its lifespan, are considered. Other potential savings and benefits include reduced need for storm sewer pipes and other stormwater practices, less developable land consumed for stormwater treatment, and ancillary benefits (improved aesthetics and reduced urban heat island effect). These systems are especially cost effective in existing urban development where parking lot expansion is needed, but there is not sufficient space for other types of BMPs. They combine parking, stormwater infiltrationThe slow movement of water into or through a soil or drainage system.Penetration of water through the ground surface., retention, and detentionThe temporary storage of stormwater to control discharge rates, and allow for sedimentation. into one facility.

Incentives and Credits [12]

Objective

The key objective of the StormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. Credit Program is to recognize property owners who have implemented stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. and/or pollution prevention best management practices (“BMPs”) to reduce impacts to the City’s stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. infrastructure by controlling the quantity and quality of stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. leaving their property.

Principles

The StormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. Credit Program is designed according to the following guiding principles:

  • Available to every non-residential and multi-residential property (including those considered “mixed-use”) in Mississauga, unless otherwise exempt from stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. charges or receiving a subsidy to offset stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. charges.
  • A clear linkage exists between the credit amounts provided and cost savings to the City’s stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. program resulting from the implementation of BMPs.
  • Property owners have the flexibility to pursue practices that suit the needs of and opportunities on their property.

Eligibility

All multi-residential and non-residential properties (including mixed-use properties) are eligible for the credit program, except for any portion thereof which is receiving an exemption or subsidy reduction to the stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. charge. Single residential properties are not eligible for the credit program.

Credit Schedule

StormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. credits are available in each of four categories, which align with the overarching objectives of the City’s stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. program as shown in the following table.

Category Evaluation Criteria Total Credit (50% Maximum)
Peak Flow Reduction Percent reduction of the 100-year post development flow to pre-developmentrefers to the characteristics and functions of a system prior to urban development. conditions of the site Up to 40% To a total of no more than 50%
Water Quality Treatment Consistent with Provincial criteria for enhanced treatment Up to 10%
RunoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. Volume Reduction Percent capture of first 15 mm of rainfall during a single rainfall event Up to 15%
Pollution Prevention Develop and implement a pollution prevention plan Up to 5%

A maximum of 50% credit can be achieved by a property owner or operator. The 50% cap reflects the maximum proportion of the City’s stormwaterSurface runoff from at-grade surfaces, resulting from rain or snowmelt events. program in terms of cost that may be beneficially impacted by on-site BMPs. The balance of the City’s program requires funding regardless of BMPs that may be in place on private and public lands.

References

  1. PorosityThe porosity (n) of a mixture is the ratio of the volume of void-space to the total or bulk volume of the mixture. It is closely related to the concept of void ratio (e) where void ratio is the ratio of the volume of void-space to the volume of solids. n = Volume of voids/Total volume of mixture = e/(1+e) of Structural Backfill, Tech Sheet #1, Stormtech, Nov 2012, http://www.stormtech.com/download_files/pdf/techsheet1.pdf accessed 16 October 2017
  2. 2.02.12.2 Judge, Aaron, "Measurement of the Hydraulic Conductivity of Gravels Using a Laboratory Permeameter and Silty Sands Using Field Testing with Observation Wells" (2013). Dissertations. 746. http://scholarworks.umass.edu/open_access_dissertations/746
  3. Roger T. Kilgore and George K. Cotton, (2005) Design of Roadside Channels with Flexible Linings Hydraulic Engineering Circular Number 15, Third Edition https://www.fhwa.dot.gov/engineering/hydraulics/pubs/05114/05114.pdf
  4. Simcock, R and Dando, J. 2013. Mulcha top dressing over vegetation beds that provides suppresses weeds and helps retain soil moisture in bioretention cells, stormwater planters and dry swales. specification for stormwater bioretentionA shallow excavated surface depression containing prepared filter media, mulch, and planted with selected vegetation. devices. Prepared by Landcare Research New Zealand Ltd for Auckland Council. Auckland Council technical report, TR2013/056
  5. Newman AP, Coupe SJ, Spicer GE, Lynch D, Robinson K. MAINTENANCE OF OIL-DEGRADING PERMEABLE PAVEMENTS: MICROBES, NUTRIENTS AND LONG-TERM WATER QUALITY PROVISION. https://www.icpi.org/sites/default/files/techpapers/1309.pdf. Accessed July 17, 2017.
  6. Paul P, Tota-Maharaj K. Laboratory Studies on GranularGravel, or crushed stone of various size gradations (i.e., diameter), used in construction; void forming material used as bedding and runoff storage reservoirs and underdrains in stormwater infiltration practices. Filters and Their Relationship to Geotextiles for Stormwater Pollutant Reduction. Water. 2015;7(4):1595-1609. doi:10.3390/w7041595.
  7. ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1860 MATERIAL SPECIFICATION FOR GEOTEXTILES. 2012. http://www.raqsb.mto.gov.on.ca/techpubs/OPS.nsf/0/2ccb9847eb6c56738525808200628de1/$FILE/OPSS%201860%20Apr12.pdf. Accessed July 17, 2017
  8. Bean, E.Z., Hunt, W, F., Bidelspach, D.A. 2007a. Evaluation of Four Permeable Pavement Sites in Eastern North Carolina for RunoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. Reduction and Water Quality Impacts. Journal of IrrigationHuman application of water to agricultural or recreational land for watering purposes. City of Toronto Wet Weather Flow Management November 2006 47 and Drainage Engineering. Vol. 133. No. 6. pp. 583-592.
  9. Legret, M and V. Colandani. 1999. Effects of a porous pavement structure with a reservoir structure on runoffThat potion of the water precipitated onto a catchment area, which flows as surface discharge from the catchment area past a specified point.Water from rain, snow melt, or irrigation that flows over the land surface. water: water quality and fate of metals. Water Science and Technology. 39(2): 111-117
  10. Pratt, C.J., Mantle, J.D.G., Schofield, P.A. 1995. UK research into the performance of permeable pavementAn alternative practice to traditional impervious pavement, prevents the generation of runoff by allowing precipitation falling on the surface to infiltrate through the surface course into an underlying stone reservoir and, where suitable conditions exist, into the native soil. reservoir structures in controlling stormwater discharge quantity and quality. Water Science Technology. Vol. 32. No. 1. pp. 63-69.
  11. City of Portland. 2004. Portland Stormwater Management Manual. Prepared by the Bureau of Environmental Services (BES). Portland, OR.
  12. http://www7.mississauga.ca/Departments/Marketing/stormwater/stormwater-charge/img/stormwater-credits-manual-0.1.pdf

Proprietary Links

In our effort to make this guide as functional as possible, we have decided to include proprietary systems and links to manufacturers websites.
Inclusion of such links does not constitute endorsement by the Sustainable Technologies Evaluation Program.
Lists are ordered alphabetically; link updates are welcomed using the form below.

Pre-cast

Poured in place